Australia: Q1 2025 deemed second-best quarter for financial commitment in grid-scale batteries

May 29, 2025
LinkedIn
Twitter
Reddit
Facebook
Email

Trade association Clean Energy Council (CEC) has deemed Q1 2025 the second-best quarter on record for large-scale battery energy storage system (BESS) investment in Australia.

The organisation’s Quarterly Investment Report: Large-scale renewable generation and storage Q1 2025 details six projects worth AU$2.4 billion (US$1.54 billion), representing 1,510MW/5,016MWh, that have reached the financial commitment stage.

The largest of these projects is EnergyAustralia’s 350MW/1,400MWh Wooreen BESS located in the Latrobe Valley in Victoria. Construction started on this project in February, just after financial close had been achieved.

Finnish marine and energy technology group Wärtsilä has been contracted to supply the BESS solution for the site. At the same time, balance-of-plant (BOP) contractor Zenviron will provide balance-of-plant design, construction, installation, and commissioning of the site. Tilt Renewables is developing the project.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The second-largest BESS to reach financial commitment was stage two of the 270MW/1,356MWh Supernode BESS in Queensland, which is being developed by global investment manager Quinbrook Infrastructure Partners.

Since then, the size of this BESS has increased further to 750MW/2,540MWh via an offtake agreement signed with state-owned energy company Stanwell.

The remaining BESS that secured financial commitment in the first quarter of 2025 include Copenhagen Infrastructure Partners’ 240MW/960MWh Summerfield BESS, Intera Renewables’ 250MW/500MWh Limestone Coast North Energy Park, and Amp Energy’s 150MW/300MWh Bungama BESS (stage one), all located in South Australia. Additionally, Equis Australia’s 250MW/500MWh Calala BESS is situated in New South Wales.

Financially committed storage projects by energy output, quarterly MWh. Image: Clean Energy Council.

These six projects represent a AU$2.4 billion capex investment, which is 83% higher than the revised rolling 12-month quarterly average for investment in new storage projects, currently at AU$1.3 billion.

Average duration of financially committed projects increases

The average duration of these six projects was 3.2 hours, which is an increase from the average duration of 2.2 hours for projects reaching financial commitment in Q1 2024. This coincides with Wood Mackenzie’s analysis, which estimates that longer-duration BESS, such as 4-hour duration, could become more lucrative in the National Electricity Market (NEM) in the near future.

It should also be noted that the 5,016MWh of energy storage projects that reached financial commitment in Q1 2025 appear more impressive when considering that, in the entirety of 2024, 11,348MWh reached financial commitment.

This figure was slightly lower than the record set in 2023, which was 4,663MW/11,509MWh. The total investment for these projects amounted to at least AU$3.9 billion for the year.

Construction began on three BESS projects in Q1 2025, totalling 840MW/2,860MWh. Additionally, two storage projects were commissioned this quarter, representing 56MW/98 MWh.

Investment in large-scale generation off to a slow start

Despite the positives of energy storage, investment in large-scale solar PV and wind generation in Australia, has gotten off to a slow start in 2025, after what was a very strong end to 2024.

During the quarter, two projects achieved financial close, totalling 386MW. These projects are Amp Energy’s 280MW Bungama solar PV power plant in South Australia and European Energy’s 106MW Lancaster solar PV plant in Victoria. Together, they represent a capital investment of AU$410 million.

Meanwhile, five generation projects totalling 756MW of new generation capacity completed commissioning in Q1 and are now fully operational.

Despite the shortcomings of investment in Q1 2025 compared to Q4 2024, the CEC noted that this is a common occurrence. Over the past five years, the average quarterly capacity of generation projects reaching financial commitment in Q1 has been 427MW. By comparison, the Q4 average over the past five years has been 1,153MW.

Clean Energy Council chief policy and impact officer, Arron Wood, said it was encouraging to see sustained momentum in investment for large-scale energy storage projects.

“Wind and solar combined with energy storage is the lowest-cost form of electricity generation and by installing more battery storage projects across the country, Australians can get the biggest benefits from renewable energy through cheaper, cleaner, more reliable power – while creating thousands of new jobs,” Wood said.

Read Next

Premium
November 13, 2025
On 4 September, US Immigration and Customs Enforcement (ICE), along with multiple other law enforcement organisations, raided Hyundai Motor and LG Energy Solution’s electric vehicle (EV) battery cell plant in Ellabell, Georgia, US.
November 13, 2025
Octopus Australia has achieved financial close on a AU$900 million (US$587 million) DC-coupled hybrid facility that combines 300MW of solar generation with a 243MW/486MWh battery energy storage system (BESS) in New South Wales.
November 13, 2025
Ampyr Australia has acquired the 270MW Davenport battery energy storage system (BESS) in South Australia from Green Gold Energy (GGE), renaming the facility the ‘Northern Battery’.
November 12, 2025
Energy storage developer and system integrator Energy Vault has released its Q3 2025 financial results, showing growth credited to expanding projects in Australia and its ‘Asset Vault’ subsidiary.
November 12, 2025
Three large-scale BESS with a combined capacity of 720MW have been submitted for federal assessment under Australia’s EPBC Act.

Most Popular

Email Newsletter