Ameresco and SCE agree completion for two of three California BESS projects, liquidated damages still loom

LinkedIn
Twitter
Reddit
Facebook
Email

Clean energy system integrator Ameresco and utility Southern California Edison (SCE) have agreed on damages to be paid for two battery energy storage system (BESS) projects out of a three-project order, though liquidated damages related to a substantial delay in commissioning are still being negotiated.

SCE will pay Ameresco approximately US$110 million within seven days for the milestone completion of the BESS projects. However, this reflects a set-off of liquidated damages, which are still in dispute, as well as additional work costs.

Final acceptance payments will follow upon the projects’ completion. The third and final project in the order is expected to reach substantial completion in Q4 2024.

Energy-Storage.news first reported that SCE was considering withholding liquidated damages from Ameresco in July this year (Premium access article).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The projects totalling 537.5MW/2,150MWh were meant to come online in August 2022 but have been delayed by over two years. The contract value for Ameresco was US$1.226 billion.

Ameresco issued SCE with a ‘force majeure’ claim in 2022, citing the shutdown of factories in Beijing due to Covid-19 lockdowns.

The projects are located at three distribution-level substation parcels in SCE’s service territory to provide for the electricity demands in the San Joaquin Valley, the Long Beach area and Rancho Cucamonga and nearby communities. They were specifically procured in light of emergency reliability risks due to extended drought, wildfire and heatwaves in California.

In other BESS activity, Ameresco recently completed 313MWh of projects for a utility in Colorado and landed its first job in the UK, a 624MWh project for developer Atlantic Green.

Read Next

Premium
October 19, 2026
In the wide-ranging conversation, Shaw starts off by describing the year-end rush as a perennial challenge for the battery energy storage system (BESS) sector in the US.
October 19, 2026
Four-hour battery storage is less expensive than open-cycle gas turbines in the 43 markets in which both technologies were modelled, according to a new report from market research firm Wood Mackenzie.
October 16, 2026
US energy storage developer Flatiron Energy has closed on approximately US$850 million for its 1,200MWh Energizar energy storage project in Chelsea, Massachusetts, US.
October 15, 2026
Energy storage owner-operator Nightpeak Energy has reached financial close and commercial operation on its 150MW/300MWh Bocanova 2 battery storage project in Brazoria County, Southeast Texas.
October 15, 2026
From the Midwest to New York, local and state governments are introducing new zoning rules and restrictions on BESS and data centre projects.