AGL’s 500MWh Abermain battery storage system cleared under Australia’s EPBC Act

LinkedIn
Twitter
Reddit
Facebook
Email

AGL Energy has received federal environmental clearance for a 500MWh battery energy storage system (BESS) in Queensland under Australia’s EPBC Act.

The Abermain Battery Project, which was referred with a power output of 125MW and a 4-hour duration, would be built at 161-173 Holdsworth Road, Tivoli, in the Ipswich City Council area west of Brisbane.

A decision notice found the project is “not a controlled action” under section 75 of the Environment Protection and Biodiversity Conservation (EPBC) Act, meaning it needs no further federal assessment.

The decision was made by Declan O’Connor-Cox, branch head, Environment Assessments Queensland, and lapses in November 2031 if the project has not substantially started by then.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The proponent is Abermain BESS OpCo Pty Ltd, a wholly owned AGL entity, which referred the 125MW/500MWh Abermain BESS earlier this year without proposing environmental offsets, as AGL did not consider it a controlled action.

The referral said the BESS would connect to the National Electricity Market (NEM) through Powerlink’s Abermain Substation, about 100m north-west of the site, via a new on-site 275/33kV substation and an underground line.

Powerlink, the Queensland government-owned transmission network operator, is separately developing that connection, which it would build, own and operate.

The referral described enclosed lithium-ion battery storage units with power conversion systems (PCS), transformers, inverters and switchgear.

Construction would take up to 18 months, followed by an operating life of up to 30 years. The disturbance footprint covers about 3.3 hectares, around 1.2 hectares of it degraded eucalyptus and acacia woodland, with koala-exclusion fencing among the proposed mitigation measures.

Ipswich City Council granted development approval for the project on 3 November 2023.

It was originally developed by Firm Power, which AGL agreed to acquire in August 2024 for AU$250 million (US$165.5 million), adding a 5.8GW pipeline of grid-scale projects, 2.7GW of it in Queensland.

AGL’s Queensland pipeline grows

Abermain is AGL’s second Queensland BESS to clear the EPBC Act, after the 500MW/2,000MWh Tuckeroo BESS at Hopeland in the Western Downs, which was also ruled not to be a controlled action.

Western Downs Regional Council granted development approval for Tuckeroo in March 2025, and AGL targeted commercial operation in the second half of 2027 when it referred the project.

Powerlink referred a 1.8km underground 275kV line connecting Tuckeroo to the Western Downs Substation in October 2025, as it is doing for Abermain.

AGL has since referred its 500MW/2,000MWh Mount Britton BESS near Nebo in central Queensland, where its referral said the project could directly affect species including the koala and greater glider.

In New South Wales, AGL began commissioning its 1,000MWh grid-forming Liddell BESS earlier this year, backed by AU$35 million in funding from the Australian Renewable Energy Agency (ARENA), the federal renewables funding body. It has since been brought online.

Closer to Abermain, CleanCo, the Queensland government-owned generator, opened its 250MW/500MWh Swanbank BESS in February 2026 on a former coal power station site, using Tesla Megapack units.

Firm Power also originated the 500MW/1,000MWh Blackstone Battery in Ipswich’s Swanbank industrial area, which Octopus Australia bought in October 2023 and took through Ipswich City Council planning approval in July 2025.

Other Queensland projects have received the same federal ruling. The 1,600MWh grid-forming Rutherglen Battery from Gryphon Energy, Red Hill Renewable Energy and Ampyr Energy Australia near Gladstone was found not to be a controlled action in March.

Never miss an Australian energy storage story. Sign up for our Australia newsletter and get the latest project announcements, policy updates and market analysis delivered directly to you.

26 November 2026
9am GMT / 1pm GST
In this webinar, Florian Didier and Salomé Perperot from Clean Horizon share the approach they use when supporting IPPs through optimiser selection and contract negotiation across Europe. The presentation will be followed by a live Q&A session in which attendees can put their own questions to the speakers. Who should attend: IPPs and developers, asset owners and investors, lenders and financial advisors, and anyone involved in the commercial structuring of battery storage projects.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.

Read Next

November 17, 2026
EnerVenue CEO Henning Rath discussed its first multi-MWh order, its North American push, and the policy uncertainty shaping battery manufacturing in the US.
November 17, 2026
Spain-headquartered power conversion system (PCS) manufacturer Power Electronics is supplying grid-forming inverters and DC/DC converters for Edify Energy’s Smoky Creek and Guthrie’s Gap solar-plus-storage projects in Queensland, Australia.
November 17, 2026
ASX-listed Frontier Energy has started construction on Stage 1 of its Waroona Renewable Energy Project in Western Australia (WA), which pairs solar PV with a battery energy storage system (BESS).
November 16, 2026
US energy storage developer Flatiron Energy has broken ground on its 250MW/1,200MWh Energizar Energy Storage Project in Chelsea, Massachusetts, US.
November 16, 2026
US-based BESS manufacturer NeoVolta has signed a US$116 million master purchase agreement with an unnamed “leading energy solutions provider.”