Mixed emotions in Brazil’s clean energy sector so far this month, as the national regulator postponed an important decision on the future of energy storage days after approving the country’s first co-located solar and storage facility.
Co-located plant in Bahia approved at signing ceremony
The authorisation of Brazil’s first battery energy storage system (BESS) to be co-located with solar generation was hailed as a “moment of great joy” at a signing ceremony.
Held at the beginning of this month (2 April), the ceremony celebrated the granting of authorisation by Brazil’s National Electric Energy Agency (ANEEL), for a 1MW/5MWh BESS to be deployed at the site of Sol de Brotas 7, an existing solar PV power plant.
The battery storage system will share the same grid connection as the solar PV system, which appears to be one of seven plants totalling 228MW in the northeastern state of Bahia brought into commercial operation by a subsidiary of European energy company Statkraft.
Try Premium for just $1
- Full premium access for the first month at only $1
- Converts to an annual rate after 30 days unless cancelled
- Cancel anytime during the trial period
Premium Benefits
- Expert industry analysis and interviews
- Digital access to PV Tech Power journal
- Exclusive event discounts
Or get the full Premium subscription right away
Or continue reading this article for free
The project, in the Bahian municipality Uibai, will enable electricity to be stored and delivered to the grid when required in the system’s lithium-ion (Li-ion) batteries, using a 2.3MW power conversion system (PCS) with an inverter output voltage of 0.60kV.
ANEEL noted that the BESS will charge not only from power generated by Sol de Brotas 7, but also from the grid and therefore other generation facilities in the area, including wind as well as solar.
ANEEL director-general Sandoval Feitosa described the “moment of great joy” at the agency having “fulfilled our mission,” calling batteries a medium- and short-term solution to the problem of integrating variable renewable energy (VRE) sources to the grid. This problem “will intensify over time,” Feitosa said, considering Brazil’s “vigorous growth of renewables.”
ANEEL delays could cause ‘irreparable harm,’ trade association chief says
However, the regulatory treatment of energy storage in Brazil is currently in a state of limbo. While Sandoval Feitosa spoke of the need for a regulatory framework that provides security for investors, the project was only able to be approved due to its co-location with a generation plant and considered under those applicable, existing regulations.
ANEEL has been considering the regulatory definition and treatment of energy storage facilities since it began analysis in 2019. In 2022, the regulator published a technical note which proposed creating specific rules that recognised the technical and economic characteristics of storage within the network.
While public consultations have since taken place, and Brazil’s first 30MW/60MWh standalone BESS pilot project was inaugurated in late 2022 by transmission system operator (TSO) ISA CTEEP, deliberation on proposed regulations stalled this month.
On 7 April, debate resumed following the proposals reintroduction in March. This was prompted by a request for review of the proceedings by board member Fernando Mosna.
However, ANEEL director Willamy Frota made a new request for review at that time and director-general Feitosa suggested a reopening of public consultations.
In a statement, the director of national energy storage trade association Associação Brasileira de Armazenamento de Energia (ABSAE), Fabio Lima, said that “there is no technical justification for further delays”.
Although ABSAE conceded it was the right of board members to request reviews, and thanked Fernando Mosna and another member, Gentil Nogueira, for their voting and support, the association said the process is already “mature and has been followed step-by-step by the entire board”, which made the motivation for further postponing the decision difficult to understand, it said.
According to an ANEEL update, as of 6 April, 84.81% of Brazil’s monitored power capacity is considered renewable, with 2.4GW of new electricity generation including 1.1GW of solar PV added to the grid in the first quarter of 2026.
Trade association ABSAE, meanwhile, said that energy storage adoption is crucial to address crises facing Brazil’s energy sector. These include the inflexibility of electricity generation and demand, curtailment of more than 20% of wind and solar PV generation capacity, along with the risk of nighttime and peak electricity shortages and rising electricity charges and tariffs.
“Energy storage has been studied by ANEEL since 2019, has already undergone three distinct phases of discussions, and has received an opinion from the Federal Attorney’s Office at ANEEL, which resolved the doubts of all directors,” ABSAE executive director Lima, who attended the recent signing ceremony, said.
“To revert the process to the public consultation phase at this point would cause irreparable harm to the Brazilian electricity sector. We trust that the Agency will maintain its traditional pioneering spirit and move forward quickly with the matter.”