Over 17GWh of BESS deployed globally in February 2026

March 18, 2026
LinkedIn
Twitter
Reddit
Facebook
Email

A total of 6.9GW/17.1GWh of grid-scale BESS came online last month, as per the most recent figures from Benchmark Mineral Intelligence.

The figure is a roughly 60% increase on the same figure from February 2025, when 4.5GW/10.5GWh of battery energy storage system (BESS) capacity was recorded as coming online.

For last month’s figure, around 53% was deployed in China, 9% in Europe, 15% in North America and 21% in Australia, with the smaller remainder from Asia excluding China.

This article is part of a monthly series using the data from Benchmark, which recently acquired downstream market intelligence firm Rho Motion and has now integrated it into its own brand name.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Regional figures

China has accounted for at least 50% of global deployments in most months since we started reporting on the data.

Some 4,186MW/9,140MWh came online in the country, which is by far the world’s largest battery and BESS market by both upstream manufacturing capacity and downstream deployments. Two projects over 2GWh came online there.

However the largest project to come online anywhere in February was the 2.4GWh Collie BESS in Australia, which we reported on at the start of the month. That, along with the 619MWh phase one of the Supernode project, helped the wider Oceania region have one of its best months yet.

In North America, 785MW/2,547MWh was put into commercial operation in February. We reported on major US projects coming online from Alliant Energy in Iowa, Leeward Renewable Energy in Arizona and Plus Power in Maine, plus a 1.2GWh one in Canada from Boralex.

Meanwhile in Europe some 786MW/1,497MWh came online. Benchmark said that this includes the 1GWh Coalburn BESS from Alcemi, although its completion has not been reported publicly.

Benchmark added that 161GWh entered the project pipeline in February, bringing the total announced projects over the course of the first two months of 2026 to just under 300GWh. A total of 38 giga-scale projects were announced this month, the largest of which was the 30GWh Xcel Energy Form Energy iron-air battery project in Minnesota.

The Energy Storage Summit USA will be held from 24-25 March 2026, in Dallas, Texas. It features keynote speeches and panel discussions on topics like FEOC challenges, power demand forecasting, and managing the BESS supply chain. For complete information, visit the Energy Storage Summit USA 2026.

9 June 2026
Stuttgart, Germany
Held alongside The Battery Show Europe, Energy Storage Summit provides a focused platform to understand the policies, revenue models and deployment conditions shaping Germany’s utility-scale storage boom. With contributions from TSOs, banks, developers and optimisers, the Summit explores regulation, merchant strategies, financing, grid tariffs and project delivery in a market forecast to integrate 24GW of storage by 2037.
2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.

Read Next

March 23, 2026
Eku Energy and Valent Energy have recorded separate milestones in their respective expansions of battery energy storage systems (BESS) in Australia.
March 23, 2026
Australian utility AGL has started commissioning its 500MW/1,000MWh Liddell battery energy storage system (BESS) in New South Wales.
March 23, 2026
Quinbrook Infrastructure Partners has received environmental clearance for its Supernode North battery energy storage system (BESS) project in Queensland, Australia.
March 20, 2026
Energy storage developer and system integrator Energy Vault has released its Q4 and full year 2025 financial results, showing growth credited to entering the AI infrastructure market, expanding projects in Australia and its ‘Asset Vault’ subsidiary.
March 20, 2026
Vena Energy has signed a long-term revenue share agreement with Danish energy trading company InCommodities for its 204MW/510MWh Bellambi Heights battery energy storage system (BESS) in Central West New South Wales, Australia.