Younicos to upgrade energy storage system on Kodiak Island, Alaska

LinkedIn
Twitter
Reddit
Facebook
Email
Battery upgrade on Kodiak Island. Source: Younicos
Battery upgrade on Kodiak Island. Source: Younicos

Berlin-based energy storage firm Younicos will design, install and commission an upgraded 3MW battery-based energy storage system on Kodiak Island, Alaska, pursuant to an agreement with the Kodiak Electric Association (KEA).

The upgrade will replace a lead-acid battery system that was installed in 2012 with advanced lithium-ion batteries and new battery racks, for a storage system with greater operational lifetime.

The project is expected to be completed by mid-August 2017 – in time to provide grid stability for the increased seasonal levels of wind power on the island.

“Our main goal has always been to bring more renewables to the island and greatly reduce the cost and environmental impacts of using diesel fuel,” said Darron Scott, president and CEO of KEA. “We realized early on that battery storage is the best solution to help us achieve these goals, and that Younicos is a company with the right technology and expertise – as well as a passion for clean and affordable energy.”

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“We’re grateful to be chosen once more by KEA to upgrade their battery storage facility,” said Jayesh Goyal, chief commercial officer of Younicos. “Their decision to collaborate again on this project demonstrates a high level of trust in both our company and our storage control technology.”

The upgrade to the system will improve the reliability of the grid and its balancing and frequency regulation abilities. This is ideal given that KEA has an ambitious 95% renewable energy by 2020 goal – which so far is mostly achieved through wind and hydro projects. The system upgrade will ensure that more renewables can be integrated into the grid.

Read Next

October 16, 2026
US energy storage developer Flatiron Energy has closed on approximately US$850 million for its 1,200MWh Energizar energy storage project in Chelsea, Massachusetts, US.
October 15, 2026
Energy storage owner-operator Nightpeak Energy has reached financial close and commercial operation on its 150MW/300MWh Bocanova 2 battery storage project in Brazoria County, Southeast Texas.
October 15, 2026
From the Midwest to New York, local and state governments are introducing new zoning rules and restrictions on BESS and data centre projects.
October 14, 2026
The Illinois Power Agency (IPA) is seeking stakeholder feedback on its summer procurement of 600MW of energy storage projects in the US state, after falling short by 438MW.
October 13, 2026
US tax equity syndicator Foss & Company has closed a US$58 million partnership flip transaction to finance an energy storage project in Hidalgo County, Texas, developed by GridStor.