Berlin-based energy storage firm Younicos will design, install and commission an upgraded 3MW battery-based energy storage system on Kodiak Island, Alaska, pursuant to an agreement with the Kodiak Electric Association (KEA).

The upgrade will replace a lead-acid battery system that was installed in 2012 with advanced lithium-ion batteries and new battery racks, for a storage system with greater operational lifetime.

The project is expected to be completed by mid-August 2017 – in time to provide grid stability for the increased seasonal levels of wind power on the island.

“Our main goal has always been to bring more renewables to the island and greatly reduce the cost and environmental impacts of using diesel fuel,” said Darron Scott, president and CEO of KEA. “We realized early on that battery storage is the best solution to help us achieve these goals, and that Younicos is a company with the right technology and expertise – as well as a passion for clean and affordable energy.”

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“We’re grateful to be chosen once more by KEA to upgrade their battery storage facility,” said Jayesh Goyal, chief commercial officer of Younicos. “Their decision to collaborate again on this project demonstrates a high level of trust in both our company and our storage control technology.”

The upgrade to the system will improve the reliability of the grid and its balancing and frequency regulation abilities. This is ideal given that KEA has an ambitious 95% renewable energy by 2020 goal – which so far is mostly achieved through wind and hydro projects. The system upgrade will ensure that more renewables can be integrated into the grid.

20 April 2027
Renaissance Dallas at Plano Legacy West Hotel, Dallas, Texas, Dallas
Policy, Procurement and Power Demand: Defining the Next Chapter for Energy Storage. Two days in Dallas where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into US storage, this is that room.

Read Next

October 23, 2026
Tech giant Google and distributed energy resource (DER) platform Voltus have announced an expanded agreement to build a 1GW virtual power plant (VPP) in the US.
October 22, 2026
In recent North American sodium-ion news, Hithium is entering the Canadian market with two BESS solutions, while Peak Energy has closed a Series B financing round led by GM.
October 22, 2026
Science safety leader UL Solutions has announced a new certification pathway intended to help manufacturers of modular direct current (DC) battery energy storage systems (BESS).
October 21, 2026
Distributed energy storage company Viridi and developer and financier Good Carbon Co. have announced the deployment of a 3.75MWh energy storage project in Buffalo, New York.
October 20, 2026
Zinc hybrid cathode battery and storage system maker Eos Energy Enterprises has reported its highest quarterly revenue to date alongside a narrowing gross margin loss.