Younicos to upgrade energy storage system on Kodiak Island, Alaska

February 28, 2017
LinkedIn
Twitter
Reddit
Facebook
Email
Battery upgrade on Kodiak Island. Source: Younicos
Battery upgrade on Kodiak Island. Source: Younicos

Berlin-based energy storage firm Younicos will design, install and commission an upgraded 3MW battery-based energy storage system on Kodiak Island, Alaska, pursuant to an agreement with the Kodiak Electric Association (KEA).

The upgrade will replace a lead-acid battery system that was installed in 2012 with advanced lithium-ion batteries and new battery racks, for a storage system with greater operational lifetime.

The project is expected to be completed by mid-August 2017 – in time to provide grid stability for the increased seasonal levels of wind power on the island.

“Our main goal has always been to bring more renewables to the island and greatly reduce the cost and environmental impacts of using diesel fuel,” said Darron Scott, president and CEO of KEA. “We realized early on that battery storage is the best solution to help us achieve these goals, and that Younicos is a company with the right technology and expertise – as well as a passion for clean and affordable energy.”

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“We’re grateful to be chosen once more by KEA to upgrade their battery storage facility,” said Jayesh Goyal, chief commercial officer of Younicos. “Their decision to collaborate again on this project demonstrates a high level of trust in both our company and our storage control technology.”

The upgrade to the system will improve the reliability of the grid and its balancing and frequency regulation abilities. This is ideal given that KEA has an ambitious 95% renewable energy by 2020 goal – which so far is mostly achieved through wind and hydro projects. The system upgrade will ensure that more renewables can be integrated into the grid.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

April 22, 2026
Bobwhite Energy Storage, an affiliate of independent power producer (IPP) Tenaska has signed a long-term energy storage agreement (ESA) with utility Tennessee Valley Authority (TVA) for a 225MW/900MWh project in East Tennessee, US.
Premium
April 22, 2026
We look at the potential of flow batteries for LDES and compare the leading providers’ offerings and trajectories.
April 21, 2026
US ‘multi-day’ energy storage startup Noon Energy has announced an agreement with Meta to reserve up to 1GW/100GWh of long-duration energy storage (LDES) capacity.
Premium
April 21, 2026
Energy-storage.news Premium speaks with the new CEO of nickel-hydrogen battery company EnerVenue, Henning Rath, about the company’s goals for 2026 and beyond.
April 20, 2026
In this US news roundup, Eos and Turbine-X, CPower and Vertiv, and Elevate Renewables highlight the ‘bring your own capacity’ model in data centre-focused announcements.