Utility PPA secured for first community solar-plus-storage project in Massachusetts

LinkedIn
Twitter
Reddit
Facebook
Email
A commercial rooftop solar installation elsewhere in the US. The Origis project will pair a rooftop PV system with a battery installed at ground level nearby. Image: Borrego Solar.

The addition of energy storage has made a 1MW community rooftop solar project in Massachusetts viable after a long-term PPA was secured with a local utility.

Sterling Community Solar + Energy Storage, pairing 1MW of rooftop solar PV with a 1MW / 2MWh battery energy storage system, will be constructed by Florida-headquartered Origis Energy. Origis announced yesterday that it has secured a power purchase agreement (PPA) with utility Sterling Municipal Light Department (SMLD).

Expected to be the Commonwealth state’s first completed solar-plus-storage project, capable of delivering 1.7MWh of so-called ‘baseload’ electricity each year, the community project had originally been proposed as a solar-only installation. This, however, was pushed back and didn’t happen due to the already-high penetration of solar on the local grid, which raised concerns.

Matt Stelmach, the chairman of SMLD’s board, which serves close to 4,000 residential and commercial customers and operates 160 miles of distribution lines, said that the addition of battery energy storage to make the plant’s output dispatchable had allayed some concerns about overcapacity of solar being fed into the grid at times of high production.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

“We are approaching the Light Department’s self-imposed cap on commercial solar capacity, but [the] introduction of a grid-scale battery system greatly reduces any concerns along those lines. This project is a very good match for Sterling and will greatly benefit its ratepayers,” Matt Stelmach said.

Stelmach’s SMLD colleague Sean Hamilton, a manager at the utility, said the local community offers “tremendous support” for clean energy initiatives, adding that the community aspect of the project allows the utility to open up the benefits of solar to households that might not be able to host their own rooftop system. Hamilton also said the project’s economics protect customer rates

Another key aspect of the project successfully getting underway was the effort put in by Vincent J. CampoBasso, who is a local attorney and who manages the site where the project will be installed, on land owned by a local construction company, Rockbreakers. According to Origis Energy, CampoBasso worked alongside SMLD and Origis to make it happen.

Project owner Origis will create subscription programme for community installation’s power

Construction begins later this month and is expected to take around two months, aiming for completion by the end of March. Details on equipment or components to be used have not been revealed, except that Origis will obtain batteries from a Tier 1 lithium-ion provider, as well as 4,000 PV panels, also from an unnamed Tier 1 provider.

While developer Origis Energy will also own the project, a subscription programme will be created for SMLD ratepayers, according to state policy guidelines from the Massachusetts Department of Energy Resources (DOER).

Despite SMLD’s relatively tiny size, the company has already taken steps forward in energy storage, contracting NEC Energy Solutions to supply a 2MW / 3.9MWh energy storage solution part-funded by DOER and thought to be Massachusett’s first grid-scale storage facility.

Massachusetts is one of only three US states thus far to implement a target for energy storage deployment, which while only considered ‘aspirational’ (i.e. non-binding) and dwarfed by California (1.3GW) and New York’s (1.5GW) targets at only 200MWh, nonetheless makes the state “one to watch” for the international industry.

Read Next

August 12, 2025
Massachusetts’s electric distribution companies (EDCs) and the state’s Department of Energy Resources (DOER) have launched a request for proposals (RFP) for approximately 1,500MW of mid-duration energy storage systems.
August 8, 2025
Lyten’s deal to acquire and recommence operations of European battery firm Northvolt out of bankruptcy has winners and losers, but some of the challenges that led to its demise have already been solved.
August 8, 2025
Utility Portland General Electric (PGE) announced the completion of three battery energy storage systems (BESS) totalling more than 1.9GWh in Portland, Oregon, US.
August 7, 2025
Energy storage developer and system integrator Energy Vault has received approval to pursue market-based participation in the California Independent System Operator (CAISO) with the Calistoga Resiliency Centre (CRC).
August 7, 2025
Calibrant has energised and begun generating Value of Distributed Energy Resources (VDER) credits from three front-of-the-meter battery energy storage systems (BESS) in New York, US.

Most Popular

Email Newsletter