Ukraine’s DTEK buys capacity market-winning 532MWh BESS project in Poland

LinkedIn
Twitter
Reddit
Facebook
Email

Developer Columbus Energy and Ukraine-based energy investor DTEK have agreed terms for a 133MW/532MWh BESS project in Poland, one of several to have won long-term capacity market contracts in the last 18 months.

DTEK renewable investment arm DRI has signed a preliminary agreement with Columbus to acquire the battery energy storage system (BESS) project in Chrzanów commune, southern Poland, with the transaction expected to close in mid-May.

Columbus will continue to oversee the development process until the project reaches ready-to-build (RTB) status, which is expected this year and will result in an additional bonus payment from DTEK, which has both power generation and retail utility businesses.

The 133MW power, 532MWh project won a capacity market contract in December 2022 for 125MW of its power, with an obligation to deliver from 2027. That year saw four BESS projects awarded contracts totalling 165MW, with the other three owned by developers Hynfra, OX2 and Energa Wytwarzanie (part of PKN Orlen group). Energy-storage.news interviewed Hynfra and OX2 for Premium articles last year.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The 2023 capacity market auction, for delivery in 2028, saw the amount of BESS awarded capacity jump ten-fold to around 1.7GW, with Portugal-based developer and IPP Greenvolt win 70% of this before it was acquired by private equity firm KKR, in December.

The 2022 auction saw a higher clearing price, however, of PLN 406.35/kW (US$101) versus PLN 244.9/kW (US$61) in 2023.

Around the time of the 2023 auction, research firm LCP Delta wrote that Poland would lead BESS deployments in the Central and Eastern Europe (CEE) region with around 9GW of projects awarded grid connections.

Energy-Storage.news’ publisher Solar Media will host the 2nd Energy Storage Summit Central Eastern Europe on 24-25 September this year in Warsaw, Poland. This event will bring together the region’s leading investors, policymakers, developers, utilities, energy buyers and service providers all in one place, as the region readies itself for storage to take off. Visit the official site for more info.

6 October 2026
Warsaw, Poland
The Energy Storage Summit Central Eastern Europe is set to return in September 2025 for its third edition, focusing on regional markets and the unique opportunities they present. This event will bring together key stakeholders from across the region to explore the latest trends in energy storage, with a focus on the increasing integration of energy storage into regional grids, evolving government policies, and the growing need for energy security.

Read Next

August 14, 2026
Casey Keller, founding partner at Caerus Commodities, shares critical lessons from optimising battery storage, ahead of the 2026 US Battery Asset Management Summit taking place in California on 15-16 September.
August 11, 2026
This year has seen a shift in the financing environment for merchant BESS projects in Germany for the worse.
August 5, 2026
Japanese utility Tokyo Gas has entered into a long-term offtake agreement for a 49.7MW/202.1MWh battery storage project in Fukushima Prefecture.
August 4, 2026
The largest grid-scale battery energy storage system (BESS) project in the Czech Republic has gone online, supplied by a company invested in by lithium-ion OEM CATL. 
August 3, 2026
The European Commission (EC) has approved a financial support scheme to accelerate the deployment of battery storage technologies in Slovenia.