Bi-directional EV chargers can help the grid as well as car owners, but the complexity and economic feasibility of a mass roll-out is still a challenge, the study found. Image: SolarEdge.

Domestic vehicle-to-grid (V2G) can deliver ancillary services to the UK’s electricity network and earn revenues, but what is thought to be the world’s biggest trial of the technology has found that the costs of associated hardware are still too high for many consumers.

Key findings from a three-year trial called Project Sciurus included that aggregated electric vehicles (EVs) participating in Dynamic Containment, the UK grid operator National Grid’s most recently launched frequency regulation service, could earn consumers up to £725 (US$1026) a year, but hardware costs must reduce.

The project, run by UK energy supplier OVO Energy, carmaker Nissan, low emissions transport consultancy Cenex and IT company Indra, saw between 300 and 400 vehicle-to-grid (V2G) chargers installed, a number which was lowered from 1,000 due to limits of the number of consumers with compatible EVs.

Project Sciurus found that V2G chargers could save consumers £340 compared with £120 when using one-way smart charging. Additionally, by enabling the V2G chargers to provide grid services via aggregator Kaluza’s platform, the figure rises to £513 for Firm Frequency Response (FFR) and £725 for Dynamic Containment.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

However, there are significant challenges to implementing Dynamic Containment with a portfolio of V2G chargers, with a number of conditions adding both cost and complexity. These includes the requirement for the initiated response to be within 0.5 seconds with a full response within 1 second, assets needing to be aggregated up to 1MW and 20Hz settlement to be installed, among other requirements.

Additionally, while costs of the V2G hardware have come down significantly, they are still too high both for most consumers and for the financial business case to stack up for the operator. By the end of the trial, the V2G hardware and installation cost was around £3,700 higher than that of a smart charger.

To read the full version of this story, visit Current±.

Read Next

December 19, 2025
The Australian government has expanded the nationwide Cheaper Home Batteries Program, which has seen rapid uptake from homeowners.
December 18, 2025
Distributed energy resources (DERs) are emerging as potential solutions for consumers seeking independence and relief from rising energy costs.
December 17, 2025
According to the Q4 2025 US Energy Storage Monitor from Wood Mackenzie Power & Renewables and the American Clean Power Association (ACP), 2025 energy storage installations surpassed 2024 capacity.
December 10, 2025
AFC and public-private-partnership (PPP) Cabeolica have inaugurated 13.5MW of wind power generation and 26MWh of battery storage in Cape Verde.
November 26, 2025
Technology provider Polar Night Energy and utility Lahti Energia have partnered for a large-scale project using Polar’s ‘Sand Battery’ technology for the latter’s district heating network in Vääksy, Finland.