Scotland’s first transmission system-connected battery storage project underway

By Molly Lempriere
LinkedIn
Twitter
Reddit
Facebook
Email

Zenobē has begun construction of its 50MW/100MWh battery storage asset in Scotland, said to be the first transmission connected battery in the country.

The project in Wishaw, North Lanarkshire was first announced in May 2021 and, having reached financial close, is now expected to go live by the end of 2022.

It is being financed by Santander UK. Zenobē is working with Centrica as the route to market provider, Fluence as the battery energy storage system (BESS) supplier and H&MV as the principal designer and contractor.

“This project demonstrates real innovation,” said James Basden, co-founder and director of Zenobē.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

“Scotland is leading the world in its move to renewable energy and Zenobē is proud to be providing the critical infrastructure needed for the country’s clean energy transition. Alongside our partners Fluence, Centrica, H&MV and Santander UK, we’re increasing flexibility of power supply for Glasgow and the wider network and so allowing a greater uptake of renewable energy.”

The battery will be the first in a series of major battery flexibility projects, he added, forming part of the company’s plans to invest roughly £500 million (US$624.81 million) in Scotland in the next five years.

Once operational, Centrica will optimise the battery and provide access to a variety of revenue streams for the asset.

 “We’re delighted to support Zenobē with multi-market optimisation services,” said Arno Van Mourik, director of Centrica Business Solutions International.

“We’ll leverage our proprietary FlexPond platform and trading capabilities to be in the right market at the right time, unlocking greater returns over the lifetime of the project, while supporting the decarbonisation of our power system.”

The Wishaw battery asset will also be used as part of National Grid ESO’s Constraints Management pathfinder, helping to identify and tackle challenges around transmission capacity in the region. Zenobē said that it will be the first battery in the UK to act as a flexibility tool to manage such constraints.

Zenobē is continuing to build out its battery energy storage portfolio in the UK, having also begun construction of its 100MW/107MWh battery at Capenhurst, near Chester in June 2021. This too was financed by Santander UK, following a first-of-a-kind facility between Zenobe and Santander UK in 2019.

This story first appeared on Solar Power Portal.

Read Next

September 3, 2025
Chile is leading Latin America’s wave of energy storage adoption, closely linked to its embrace of solar PV.
Premium
September 3, 2025
The UK had one of its best months of the year for large-scale BESS projects being completed in August.
September 2, 2025
The sale of the UK BESS-holding Harmony Energy Income Trust (HEIT) proved private capital’s greater patience and valuation around the asset class, the CEO of its former investment advisor told Energy-Storage.news.
September 2, 2025
“The speed at which the grid-forming inverters are operating means that standby consumption will be higher,” said Dave Bowly of AGL.