Scotland’s first transmission system-connected battery storage project underway

By Molly Lempriere
May 3, 2022
LinkedIn
Twitter
Reddit
Facebook
Email

Zenobē has begun construction of its 50MW/100MWh battery storage asset in Scotland, said to be the first transmission connected battery in the country.

The project in Wishaw, North Lanarkshire was first announced in May 2021 and, having reached financial close, is now expected to go live by the end of 2022.

It is being financed by Santander UK. Zenobē is working with Centrica as the route to market provider, Fluence as the battery energy storage system (BESS) supplier and H&MV as the principal designer and contractor.

“This project demonstrates real innovation,” said James Basden, co-founder and director of Zenobē.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Scotland is leading the world in its move to renewable energy and Zenobē is proud to be providing the critical infrastructure needed for the country’s clean energy transition. Alongside our partners Fluence, Centrica, H&MV and Santander UK, we’re increasing flexibility of power supply for Glasgow and the wider network and so allowing a greater uptake of renewable energy.”

The battery will be the first in a series of major battery flexibility projects, he added, forming part of the company’s plans to invest roughly £500 million (US$624.81 million) in Scotland in the next five years.

Once operational, Centrica will optimise the battery and provide access to a variety of revenue streams for the asset.

 “We’re delighted to support Zenobē with multi-market optimisation services,” said Arno Van Mourik, director of Centrica Business Solutions International.

“We’ll leverage our proprietary FlexPond platform and trading capabilities to be in the right market at the right time, unlocking greater returns over the lifetime of the project, while supporting the decarbonisation of our power system.”

The Wishaw battery asset will also be used as part of National Grid ESO’s Constraints Management pathfinder, helping to identify and tackle challenges around transmission capacity in the region. Zenobē said that it will be the first battery in the UK to act as a flexibility tool to manage such constraints.

Zenobē is continuing to build out its battery energy storage portfolio in the UK, having also begun construction of its 100MW/107MWh battery at Capenhurst, near Chester in June 2021. This too was financed by Santander UK, following a first-of-a-kind facility between Zenobe and Santander UK in 2019.

This story first appeared on Solar Power Portal.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

Premium
March 13, 2026
European IPP R.Power’s head of BESS and CCO sat down with Energy-Storage.news at the Energy Storage Summit 2026 last month for a video interview to discuss the firm’s storage activity and approach to procuring technology.
March 13, 2026
Australia’s MGA Thermal has secured AU$17 million (US$12 million) in new investment for its long-duration thermal energy storage technology as it enters the commercial scale-up phase.
March 12, 2026
Another busy week of BESS news from across Europe, with investors and owner-operators ABO, Field, Aspiravi, Prime Capital, Latvenergo, Sonnedix and Amarenco progressing large-scale projects across Europe.
Premium
March 12, 2026
The LDES Council’s policy team discusses the role of policy and markets in scaling long-duration energy storage globally with ESN Premium.
March 11, 2026
California’s rapid adoption of energy storage has been a major success, but market participation is complex and competitive, write Matt Drazenovich of TWAICE and Chris Swanson of Fullmark Energy.