German utility RWE has commissioned 235MWh of battery energy storage systems (BESS) in Hamm and Neurath, in the state of North Rhine-Westphalia, Germany.

The BESS, which will have a capacity of 230MW and a storage capacity of 235MWh, will consist of 690 lithium-ion battery blocks. It will require around €140 million (US$146 million) to fully develop.

RWE said the projects are scheduled to supply balancing energy to stabilise the electricity grid. The facility will also be virtually networked with RWE power stations in Germany, which will make it possible to control whether the storage units work alone or in conjunction with other power stations to supply balancing energy.

It is worth noting that this commissioning means that RWE has a global battery portfolio of around 1.2GW. This includes markets such as the US, where the German group is developing a 200MW standalone BESS in Colorado using Tesla 2XL Megapacks. RWE also recently broke ground on three BESS projects in Texas, totalling 900MWh.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

This becomes Germany’s latest large-scale BESS to be commissioned in the country. Speaking to Energy-Storage.news, battery storage developer-investor BW ESS executive director Roberto Jimenez said the country was the “hottest market in Europe today from a development perspective.”

The country’s government introduced its first Electricity Storage Strategy in late 2023, and research commissioned by BESS system integrator Fluence around that time from consultancy Frontier Economics found that with a supportive policy framework in place, Germany’s cumulative installs could rise to 15GW/57GWh by 2030 and to 60GW/271GW by 2050.

The German market is also evolving in numerous other ways. In a post on LinkedIn, Fluence senior manager of policy and market development Lars Stephen pointed to the first GWh-scale projects soon to come online, 4-hour systems coming to market, the fact that the market is still not yet saturated and DSOs increasingly opting for BESS as four major trends for 2025.

Several clean energy developer-operators have entered the market in recent years as well, including the likes of Gore Street CapitalAquila Clean Energy and Nofar Energy. BESS specialists like Eco Stor and Terralayr have entered the scene too.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

September 18, 2026
In this US news roundup, Eos has received an advance on its DOE loan, FlexGen and Lighshift have partnered on 16 BESS projects, and Georgia Power has energised a 128MW BESS.
September 18, 2026
US battery energy storage system (BESS) developer-operator Jupiter Power has closed a US$1.4 billion financing, supporting 10 US BESS projects totalling 3,600MWh of capacity.
September 18, 2026
A roundup of some of our key takeaways from the Energy Storage Summit Germany this week, including around FCAs, inertia, the capacity market (CM), EU restrictions on China, and the future of one very notable system integrator.
Premium
September 17, 2026
Energy-Storage.news Premium speaks with Randolph Mann, CEO at developer esVolta at the 2026 US Battery Asset Management Summit in Garden Grove, California.
September 17, 2026
The transition of battery energy storage systems (BESS) from development to operations remains fraught with technical gaps and communication breakdowns.