Recurrent Energy sells 200MWh Texas BESS to Hunt Energy Network

LinkedIn
Twitter
Reddit
Facebook
Email

Energy storage developer and subsidiary of Canadian Solar, Recurrent Energy, has sold its 200MWh Fort Duncan battery energy storage system (BESS) project, located in Texas, US, to developer Hunt Energy Network.

Situated in Maverick County, Texas, the 100MW/200MWh (2-hour duration) Fort Duncan Battery Storage began commercial operations in June 2025. The company previously announced that it secured US$183 million in project financing and tax equity for the facility. It expects to recognise the revenue from the sale in the first quarter of this year.

In August 2024, Energy-Storage.news Premium reported that Recurrent was seeking a loan from North American Development Bank (NADBank) to finance the Fort Duncan project.

Black Mountain Energy Storage (BMES) initially developed the Fort Duncan BESS facility before Recurrent took over it as part of a two-project portfolio in June 2022.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

e-Storage, another Canadian Solar subsidiary, supplied the energy storage systems for the project, while engineering, procurement, and construction (EPC) contractor Burns & McDonnell constructed the project.

Fort Duncan Storage operates on a merchant basis, and Recurrent claims it has established itself as a top-performing standalone BESS in the Electric Reliability Council of Texas (ERCOT) South load zone, “providing critical grid support and reliability services to the South Texas region.”

Hunt Energy Network is a subsidiary of Hunt Energy Enterprises, a disruptive energy technologies investor. Hunt Energy Enterprises is part of a larger group of family-owned companies engaged in activities ranging from oil & gas exploration to private equity investment.

Hunt Energy Network said in a release that the acquisition of the Fort Duncan project brings the company’s ERCOT BESS portfolio to a combined capacity of 420MW, across 33 projects.

In 2024, Hunt Energy Network secured a US$250 million funding commitment from Manulife Investment Management for a portfolio of projects including energy storage and thermal peaking capacity.

In 2025, Recurrent closed US$825 million in construction financing and tax equity for the Desert Bloom Storage and Papago Solar facilities in Arizona. Both projects are located in Maricopa County and are part of a multi-project partnership with utility Arizona Public Service (APS).

The Energy Storage Summit USA will be held from 24-25 March 2026, in Dallas, TX. It features keynote speeches and panel discussions on topics like FEOC challenges, power demand forecasting, and managing the BESS supply chain. ESN Premium subscribers can get an exclusive discount on ticket pricesFor complete information, visit the Energy Storage Summit USA website.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
15 September 2026
Berlin, Germany
Launching September 2026 in Berlin, Energy Storage Summit Germany is a new standalone event dedicated to Germany’s energy storage market. Bringing together investors, developers, policymakers, TSOs, manufacturers and optimisation specialists, the Summit explores the regulatory shifts, revenue models, financing strategies and technology innovations shaping large-scale deployment. With Germany targeting 80% renewables by 2030, it offers a focused platform to connect with the decision-makers driving the Energiewende and the future of utility-scale storage.

Read Next

July 31, 2026
Thermal energy storage (TES) technology provider Antora Energy has closed a US$550 million Series C funding round to accelerate deployment of its thermal battery storage systems for industrial facilities and data centres in the US.
July 31, 2026
Environmental services company Veolia has been selected to operate and maintain a 350MW microgrid to power an AI data centre campus in New Albany, Ohio, US, which includes a 430MWh BESS.
July 30, 2026
Infrastructure and construction company Aecon Group has executed an agreement with Ontario’s Independent Electricity System Operator (IESO) for the 150MW/1,200MWh Simcoe energy storage project in Norfolk County, Ontario.
July 30, 2026
IPP Eolian has begun construction on Flint Grid, a 200MW/1.06GWh energy storage project in Jersey Township, Licking County, Ohio, US.
Premium
July 30, 2026
How do Chinese OEMs respond to evolving customer requirements and new risks that come with business outside their home market? We sat down with executives from Rept Battero at Intersolar in June to discuss.