The latest auction for the UK’s Capacity Market cleared at a record low price at the end of last week as battery storage projects seemingly struggled to compete.

A total of 50.4GW of capacity was procured in National Grid’s T-4 auction to ensure capacity meets expected demand for the 2021/22 winter period, at a clearing price of just £8.40 (US$11.59) /kW per year, a record low for the T-4 auction and nearly one-third of last year’s T-4 auction clearing price of £22.50.

That low clearing price has seemingly limited the amount of new build capacity brought forward in the auction. Of that 50.4GW, just 762MW comprises new build generators, equivalent to just 1.5%.

CCGTs have predictably picked up the largest share of awarded capacity. More than 23GW – roughly 46% – has been shared between 44 different units. Its nearest competing technology by capacity is nuclear with 16 generators sharing just shy of 8GW worth of capacity.

Battery storage meanwhile only won 153MW of contracts with both the low clearing price and new de-rating factors combining to make it more difficult for the technology to compete.

A total of 3.3GW of battery storage was prequalified for the T-4 auction, de-rated to 1.344GW to account for their duration. This means that just 11% of battery storage projects secured CM contracts in this auction.

A total of 23 batteries won capacity contracts, some of which have successfully procured contracts in both last week’s T-1 auction and 2016’s Enhanced Frequency Response (EFR) tender.

Infrastructure-building group Arenko has proven to be the big winner in the battery storage field with four of its battery storage projects winning 15-year contracts for a total of 73.559MW, roughly half of the total capacity won by batteries.

Other winners in the battery storage field include solar developers British Solar Renewables and Lightsource.

Demand side response (DSR) operators procured 1.2GW of tendered capacity. Big names in the space like Limejump (36.2MW), Enernoc (287.4MW), Endeco – now known as Gridbeyond – (114.2MW), Flexitricity (214.6MW) and Kiwi Power (276MW) were all successful, alongside utilities E.on, EDF and Npower.

Interestingly, interconnectors have increased their stake in the T-4 auction to take just over 9% of procured capacity, equivalent to around 4.5GW, 2.15GW of which is new interconnection capacity.

Those results mean that interconnectors, some from continental Europe, look set to play an increasingly important role in providing security of supply in the coming years against a backdrop of uncertainty over the UK’s future participation in the  single electricity market (SEM).

The UK’s future energy relationship with Europe has proven to be a particularly contentious issue, with prominent bodies like the House of Lords and the Committee on Climate Change warning against both the effects of a botched Brexit and what it may mean for energy imports.

Meanwhile, coal has continued to witness its influence decline. Just 3GW of coal/biomass firing capacity was procured in this week’s auction with 7.6GW of capacity having exited.

Questions and comments from stakeholders

“This year’s auction shows that there is clearly more than enough capacity on the grid, and that we can keep the lights on even without resorting to the oldest and most toxic form of power generation,” Jonathan Marshall, energy analyst at the Energy and Climate Intelligence Unit, said with reference to coal.

“This takes us to four auctions without significant new large gas plants coming to fruition, which was once thought to be needed as a bridge towards a low-carbon power system. Utilities and lobbyists claim that these are needed for the future, yet legal carbon restrictions show they will face limited running hours into the 2020s and likely end up funnelling losses onto balance sheets – even if they could pick up capacity payments.

“Big gas plants are not needed to bridge the gap between coal and renewables, especially in the light of unprecedented falls in the cost of wind and solar power, which will lead to lower bills for homes and businesses going forwards,” he said.

Michael Phelan, chief executive at demand side response provider Endeco/Gridbeyond, said that the auction represented a “seismic shift” in National Grid’s attitude to capacity, arguing that the market was now valuing flexibility rather than simple capacity.

“The ability to swiftly adjust and accurately control consumption, rather than the blunt delivery of power onto the system with lots of advanced notice, is of greater significance.

“The value being so close to that of last week’s T-1 indicates that the market is flooded with available capacity. The types of capacity will drive the next challenge that National Grid faces. With the proliferation of renewables, the issues now revolve around how firm the generation is and how to counter that with flexibility, rather than the amount of available power,” Phelan said.

Just 5% of new build generators prequalified for the auction won capacity contracts, a statistic which led Phelan to conclude that “the days of high prices and the encouragement of new generation plants are behind us.”

Chaitanya Kumar, senior policy adviser on low carbon energy for think tank Green Alliance, said change was needed.

“Unfortunately, the capacity market is still failing to support flexible technologies like battery storage in favour of large centralised fossil fuel generation. It’s time the government revisited the rules so the market can support the low carbon energy system we need for the future”.

Read Next

October 21, 2021
Developer Penso Power has signed a new agreement with global maritime group BW Group that will see the build-out of the former’s UK battery storage pipeline fully funded.
October 20, 2021
Pivot Power’s 50MW/50MWh lithium-ion battery storage site in Oxford is the first tertiary connection in the UK to export to the grid.
October 18, 2021
A battery energy storage system (BESS) will be retrofitted to a utility-scale solar PV power plant in Vietnam, in a pilot project aimed at supporting the spread of renewable energy in the country while reducing power losses. 
October 14, 2021
Energy-Storage.news proudly presents this sponsored webinar with consultancy Clean Horizon, discussing why Greece can be an important European market for energy storage.
October 13, 2021
Harmony Energy Income Trust (Harmony), a battery storage investment fund operated by UK renewables and energy storage developer Harmony Energy, intends to undertake an initial public offering.

Most Popular

Email Newsletter