NV Energy and EDF sign PPA for Nevada solar plant with 180 MW / 720MWh battery storage

LinkedIn
Twitter
Reddit
Facebook
Email

Independent power producer EDF Renewables North America has signed a 22-year power purchase agreement with utility NV Energy for a 200MWac solar project coupled with a 180MW, four-hour battery storage system (720MWh).

Located around 35 miles northeast Las Vegas, Nevada, the Chuckwalla Solar+Storage project is expected to come online by the end of 2023. For context, the project is slightly smaller than the PG&E-Tesla Moss Landing substation battery project (182.5MW / 730MWh) which has just begun construction in California’s Monterey County, currently one of the biggest lithium-ion battery projects in development in the world – and set to be eclipsed by a 1,000MWh+ facility in the same region under development by Vistra Energy.

Meanwhile in May, authorities gave approval to the US$1 billion Gemini Solar Project in Nevada, a hybrid resources project combining 690MW of solar PV with a 380 MW / 1,400MWh of battery storage, again with NV Energy as the offtaker.

“The battery and solar system work together to provide more energy during the summer evening peak hours when system needs are the greatest,” said Ian Black, vice president, west region development at EDF Renewables North America.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“NV Energy can utilise the battery at their discretion in all months of the year, allowing mitigation of demand spikes.”

Plans for the Chuckwalla plant and two other Nevada solar farms were announced by NV Energy last week. The three solar-plus-storage projects, which form part of the utility’s Integrated Resource Plan (IRP) filing, total 478MW of new solar photovoltaic generation and 338MW of battery storage.

The Chuckwalla collaboration builds on the 2019 agreement between EDF Renewables and NV Energy to develop the Arrow Canyon Solar+Storage project, also located in Nevada.

EDF Renewables’ North American portfolio consists of 16GW of developed projects and 10GW under service contracts.

This story first appeared on PV Tech. Additional reporting for Energy-Storage.news by Andy Colthorpe.

Read Next

August 4, 2026
The largest grid-scale battery energy storage system (BESS) project in the Czech Republic has gone online, supplied by a company invested in by lithium-ion OEM CATL. 
August 4, 2026
IPP Prosalia has commissioned a 15MW/60MWh battery storage system at a solar PV plant in Portugal, while power group EDP has added one to a hybrid wind and solar project in Spain.
July 31, 2026
The State Council of China recently released the 15th Five-Year Carbon Peaking Action Plan, outlining a roadmap for carbon peaking through the Action Plan period.
July 29, 2026
NextEra Energy recorded a 9.5% increase in its net earnings in Q2 2026, as the company advanced its plan to merge with Dominion Energy to form the world’s largest regulated power utility.
Sponsored
July 28, 2026
We caught up with Kevin Huang, Senior Vice President and President of Energy Storage Product Line at Envision Energy at Smarter E in Munich for a video interview on the company’s energy storage strategy and the growing role of AI data centres in power demand.