NextEra’s 300MWh co-located BESS in Iowa approved by regulator

August 3, 2022
LinkedIn
Twitter
Reddit
Facebook
Email

Iowa’s energy regulator has approved two projects from NextEra Energy Resources including a 300MWh co-located battery energy storage system (BESS).

The Iowa Utilities Board (IUB) said it will grant certificates of public convenience, use and necessity for the two projects from energy supplier NextEra once they have been approved by the Linn County Board of Supervisors.

The projects are Duane Arnold Solar, a 50MW solar PV facility, and Duane Arnold Solar II, a 150MW solar PV plant with a 75MW/300MWh BESS (the size limits of the projects as per the IUB’s order).

The projects are close to the Duane Arnold nuclear station near Palo in Linn County, a facility majority-owned by NextEra which shut down in August 2020. This allows them to use the existing grid infrastructure and connections at the location, which falls within the remit of grid operator Midwestern Independent System Operator (MISO).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

As previously reported by Energy-Storage.news, NextEra already has a deal in place to sell the projects to utility Alliant Energy once operational, which is expected in 2024.

According to the IUB’s order document, the four-hour BESS at Duane Arnold Solar II will consist of 96 containers with space for an additional 48 battery containers for use in the future, as the capacity of the battery cells diminishes over time. It added that the BESS will serve to complement the solar facility by smoothing, shifting and firming the solar generation.

In a piece of concurrent news, Alliant Energy has turned a separate 5MW BESS project online in Cedar Rapids, also in Iowa, next to its Deer Run substation. It more than doubles Alliant’s BESS power in the state from 3.5MW to 8.5MW. The utility also operates in Wisconsin.

“While Alliant Energy has operated battery storage systems for several years, battery technology has advanced by leaps and bounds enabling new projects to deliver greater efficiency, performance and affordability,” said Mayuri Farlinger, vice president of customer and community engagement at Alliant Energy.

A press release said the 5MW BESS unit would store energy from the grid at times of the day when demand is low and release it when it’s needed to power homes and businesses. The company also plans to closely study the BESS system’s performance, design features and grid integration.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

April 9, 2026
Maxxen managing director Ruben Valiente speaks with Energy-Storage.news editor Andy Colthorpe at Energy Storage Summit 2026 in London.
Premium
April 8, 2026
A panel at the 2026 US Energy Storage Summit in Dallas, Texas, discussed the “creative, innovative structures” developers are having to embrace to secure long-term revenues for energy storage projects.
April 8, 2026
IPPs Zelestra, BNZ and ALFI have secured offtake and financing to hybridise solar projects with BESS across Spain, Italy, Portugal and Romania. 
April 7, 2026
Carbon dioxide-based long-duration energy storage (LDES) company Energy Dome and digital infrastructure company New Era Energy & Digital (NUAI) have signed a memorandum of understanding (MOU) to deploy Energy Dome’s CO2 Battery Plus technology in Odessa, Texas.
Premium
April 7, 2026
The project represents a US$128.6 million investment and is scheduled to begin construction this year, with commercial operations commencing in December 2026.