World’s first floating wind farm will have 1.3MWh battery system from Younicos

LinkedIn
Twitter
Reddit
Facebook
Email
Illustration of how the project is laid out. Image: Statoil.

Norwegian oil and gas company Statoil’s Batwind project in Scotland, combining wind turbines with energy storage, will have a battery system installed by system integrator Younicos.

Batwind is under development through a partnership between Statoil and Masdar, the renewables and energy efficiency company owned by a government investment group in the United Arab Emirates’ Abu Dhabi. A Memorandum of Understanding (MoU) was signed by parties including Statoil and the Scottish government to develop the project in March 2016.

The project also hosts the world’s first floating wind turbines, based on Statoil’s proprietary Hywind platform, with the wind farm portion of the project dubbed Hywind Scotland. The floating turbines generate 30MW of electricity and began production in mid-October, when the facility was officially opened by Scotland’s First Minister Nichola Sturgeon.

The offshore power plant, some 25km off the coast of Aberdeenshire to the east of the Scottish coast, is 75% owned by Statoil and 25% by Masdar. Statoil announced yesterday that it has awarded Younicos the contract to deliver a battery energy storage system of 1MW / 1.3MWh to connect to Hywind Scotland.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The battery is intended to maximise the output of the wind farm usable by the grid, which in times of overproduction could mean storing the energy generated for injection into the grid later, could smooth out the variable generation of the six 5MW Siemens Gamesa-supplied turbines and otherwise mitigate peaks and troughs in energy production. Younicos has in the past sourced batteries from Samsung SDI and others, acting as integrator for grid-scale and commercial energy storage projects, using its own energy and battery management software and control platforms.

“As part of Statoil’s strategy of gradually supplementing our oil and gas portfolio with profitable renewable energy, getting to understand energy storage is important. With more renewables coming into production it will be crucial to handle storage to ensure predictable energy supply in periods without wind or sun,” Statoil director of development for Hywind projects, Sebastian Bringsværd said.

“Batwind has the potential to add value by mitigating periods without wind – and by that making wind a more reliable energy producer year around. This could expand the use and market for wind and renewables in the future.”

The battery energy storage system will be housed in two 10ft containers, scheduled for completion by the second quarter of 2018. When the project – considered to be a pilot of the technologies involved – was first announced, Statoil said the decision to build a floating wind farm would trigger investment of around NOK2 billion (US$240 million) and creating a cost reduction of up to 70% from the first Hywind demonstration project Statoil deployed in Norway.

Growing case for wind-plus-storage

While solar-plus-storage has garnered headlines and acclaim across the clean energy industries over the past couple of years, announcements of batteries and other energy storage integrated or co-located with wind power have also become more frequent.

To name but three, Toshiba and NRG Energy recently powered up a wind-plus-storage solution in Texas, the world’s planned ‘tallest wind turbine’ installation in Germany looks likely to get a co-located pumped hydro storage and our reporter David Pratt recently went to see Vattenfall’s 22MW battery system at a wind farm in Wales, in the UK, last month.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

July 22, 2026
Delta Capacity has brought online the Nordic region’s biggest project to date and has acquired another project that would be almost twice the size.
July 20, 2026
The shareholders of the 900MW Waltrop BESS project in Germany have approved key infrastructure works for the project, with full construction scheduled for the next few months.
July 20, 2026
UAE state-owned IPP Masdar has reached financial close on what it has claimed is the world’s “first gigascale 24/7 renewable energy project”.
July 20, 2026
The European Commission has released its final Electrification Action Plan, reaffirming its belief that the bloc needs 200GW of energy storage by 2030.
July 19, 2026
Australian Prime Minister Anthony Albanese has said that large-scale data centres will be legally required to put at least as much energy into the grid as they draw from it, and that this supply must be renewable energy.