Long duration flow battery manufacturer CellCube will bring its large-scale vanadium redox flow systems to the UK, with the country’s Capacity Market firmly in its sights, according to Immersa, which the Canadian energy storage company has signed up to partner with.

UK-based solutions provider Immersa is to offer the vanadium redox flow systems to its customers in the British market. Robert Miles, Immersa’s chief executive, pointed towards a market trend towards longer duration batteries as the two companies announced the strategic partnership.

“We have been active in the UK storage sector for nearly three years and have already seen an enormous change in the application of the technology and the revenues that are derived from them.

“We have designed systems that used multiple generation technology and by installing in combination with these long duration batteries, we have shown that it is both possible and commercially feasible to generate, store and consume power that has been self-produced,” he said.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

A significant driver for longer-duration batteries in the UK market has been transmission system operator National Grid’s de-rating factors, applied to battery storage projects that bid for contracts in the Capacity Market.

As administrator of the mechanism, National Grid applies a de-rating factor based on the project’s duration, ranging from 30 minutes to four hours; the maximum expected length of a system stress event.

Batteries capable of discharging for the full four hours stand to receive the highest level of support under the mechanism, a factor which has led many developers – including Anesco – to explore the possibility of adopting longer duration, but higher cost, battery technologies like vanadium flow machines.

Flow machines have already been installed within several energy storage projects in the UK, with redT the early market leader. Last year water utility Anglian Water penned a deal with redT which will see it use flow machine-based energy storage units to optimise the solar generation at one of its facilities as part of a “pathfinder for future projects”.

Stefan Schauss, president at CellCube, said the Immersa deal strengthened the manufacturer’s strategy to target large scale energy storage infrastructure projects.

“The capacity driven markets in the UK with its many solar and wind farms is our next focus market to enable large storage infrastructure projects in their neighbourhood delivering high value streams to asset owners. Immersa and CellCube are inviting potential clients to jointly talk about options and benefits that are available through renewable energy and battery storage solutions,” he said.

Read our two-part feature article on flow batteries including potential routes to market, ‘Long Time Coming’, which profiled four makers of different long duration energy storage systems based on the technologies. (Part 1, Part 2)

Read Next

February 11, 2026
Netherlands-based iron-air long-duration energy storage (LDES) startup Ore Energy has completed a grid-connected pilot of its 100-hour iron-air LDES system at EDF Lab les Renardières in France.
Premium
February 11, 2026
Owner-operator Fidra Energy came out of virtually nowhere to be building one of Europe’s largest BESS in the UK, the 1.4GW/3.1GWh Thorpe Marsh project. We catch up with CEO Chris Elder, about its strategy and projects but also broader BESS and clean energy financing trends.
February 10, 2026
Energy infrastructure platform Revera Energy has completed an expanded US$150 million credit facility to accelerate development and construction of its battery storage, solar, and green hydrogen project pipeline across Australia and the UK.
February 9, 2026
Europe’s energy storage market has hit a turning point. What was once a scattered, early-phase market featuring pilot projects and daring developers has swiftly evolved into a dynamic, capital-intensive infrastructure sector, writes Wood Mackenzie research associate Cecilie Kristiansen.
February 6, 2026
Home battery storage and virtual power plant (VPP) specialist Lunar Energy has raised US$102 million in an oversubscribed Series D financing round led by B Capital and Prelude Ventures.