Centrica, one of the UK’s largest energy companies, is celebrating a “major breakthrough” as its flexibility trading platform goes live.

The platform allows both the UK’s transmission system operator, National Grid ESO, and one of its distribution network operators (DNOs), Western Power Distribution (WPD), to simultaneously procure flexibility. It is the first platform to allow two operators to do this in the world, Centrica said.

Whilst the flexibility being traded is from a range of sources, storage has a large role to play in the local energy market (LEM) trial.

A 1MWh redT vanadium redox flow battery system was installed in 2017. RedT is currently in the middle of a merger with US vanadium redox flow battery maker Avalon Battery, a move which now has the backing of vanadium producer Bushveld Minerals.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Sonnen – which was acquried by Shell in February – also has batteries involved in the project. The residential batteries have three capacities: 5kW, 7.5kW and 10kW, and have been paired with solar PV in 100 homes.

Over 125 businesses were also kitted out with a variety of flexible low carbon energy technologies and monitoring technology, including solar and storage, as well as combined heat and power units among other technologies.

This flexibility is now being traded through Centrica’s trading platform, which allows both WPD and National Grid ESO to place bids for flexibility services. They can both indicate when they will need an increase or decrease in generation or consumption to balance the grid or manage a local network constraint.

These bids are then matched with offers from sellers through auctions that can run from months in advance to intraday. Sellers receive a financial reward for their services.

A clearing engine has been built by Belgian advanced analytics company N-SIDE, which takes the bids and offers and finds the optimal clearing solution, taking into account grid and asset constraints.

The transmission and distribution networks are able to co-ordinate their procurement to avoid conflicting signals, making it the first time ever both have traded for flexibility on the same third platform, Centrica said.

Colm Murphy, electricity market change development manager at National Grid ESO, said the potential is “really exciting” as the system operator looks to unlock more flexibility and greater cost benefits for consumers.

“Exploring the provision of flexibility through a local energy market is a first for us and even though we’re in the early stages of the trial, we’re looking forward to evaluating the results.

The LEM is being part funded by the European Regional Development Fund and the trials are expected to be complete in spring 2020.

Jenny Woodruff, project manager at WPD, said “This phase enables Distribution Network Operators and National Grid ESO to purchase flexibility services from the same pool of resources but also introduces checks to make sure our respective services don’t counteract or interfere with each other.

“This is expected to be increasingly important as we plan to make increasing use of flexibility services, which in turn raises the chances of conflicts occurring. It’s potentially a significant problem, so this trial is an exciting step to find a solution.”

Read Next

January 21, 2026
The UK market saw strong interest and activity in 2025 but now appears to be shifting from a development market to one focused on execution, writes Solar Media analyst Charlotte Gisbourne.
January 21, 2026
Another roundup of European grid-scale BESS project news, led by MORE and Zenobe putting Greece and UK projects into operation, and major project financings/construction starts by Acacia in France, Greenvolt in Hungary and Eco Stor in Germany.
January 20, 2026
While the UK grid-scale BESS market continues to be among the busiest in Europe, there are still huge questions and plenty work to be done in several key policy areas.
Premium
January 19, 2026
US-based iron-sodium battery manufacturer Inlyte Energy has successfully completed a factory acceptance test of its first field-ready battery at its facility near Derby, UK, witnessed by representatives from US utility Southern Company.
January 19, 2026
FranklinWH and ConnectDER have had their respective battery and electric meter technologies enrolled into programmes in Arizona expected to accelerate the take-up of home batteries for virtual power plants (VPPs).