Trio of solar project approvals brings Nevada utility NV Energy up to 1,000MW storage target

LinkedIn
Twitter
Reddit
Facebook
Email
Existing NV Energy solar farm. Image: NV Energy via Facebook.

Utility NV Energy has had plans for three large-scale solar-plus-storage projects approved by regulator the Public Utilities Commission of Nevada (PUCN) which the company said will enable it to achieve a PUC-set energy storage deployment target.

NV Energy filed plans for the three solar farms in July as part of its integrated resource plan (IRP), as first reported by our sister site PV Tech. Comprising 478MW of solar PV and 338MW of battery storage, the utility said today that the addition of the projects brings NV Energy’s portfolio of solar and storage projects in service and under development to 2,669MW of new solar and 1,028MW of storage.

The PUCN target was set in March this year and mandated for NV Energy to deploy 1,000MW of energy storage. Nevada became the sixth US state to adopt such a goal, although Virginia has since become the seventh.

Notably, all three of the projects approved by PUCN yesterday include four hours of battery storage duration. NV Energy said in a press release that it will use the batteries to store cheap solar energy during the day and discharge it into the evening. The projects are scheduled to come online before the end of 2023.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

PUCN also approved a community solar project at a high school which will be the first project developed through Nevada legislature’s Expanded Solar Access programme, which requires the utility to expand solar access for low-income and disadvantaged communities. A plan to expand transmission lines also filed by NV Energy in its IRP is still under review by the PUCN.

In October NV Energy also filed a request for proposals (RfP) for “major additions” to its renewable energy portfolio with solar, geothermal, wind, biomass and biogas technology projects compliant with Nevada’s existing renewable portfolio standards to be considered, while the utility said it would also consider proposals for both standalone energy storage systems and generation projects co-located with energy storage.

The three approved projects:

Project name Generation capacity Battery storage output and capacity Location Developer
Dry Lake Solar 150MW solar PV 100MW four-hour (400MWh) Clark County, Nevada NV Energy
Boulder Solar III 128MW solar PV 58MW four-hour (232MWh) Clark County, Nevada 174 PowerGlobal + KOMIPO America
Chuckwalla Solar Project 200MW solar PV 180MW four-hour (720MWh) Clark County, Nevada EDF Renewables North America

Read Next

August 6, 2026
Denmark-headquartered multinational energy company Ørsted has put its 250MW/500MWh Old 300 energy storage project in Needville, Texas, US into operation.
August 4, 2026
The largest grid-scale battery energy storage system (BESS) project in the Czech Republic has gone online, supplied by a company invested in by lithium-ion OEM CATL. 
August 4, 2026
Massachusetts’s Department of Energy Resources (DOER) has issued a request for proposals (RFP) for 1,000MW of energy storage in the US state.
August 4, 2026
IPP Prosalia has commissioned a 15MW/60MWh battery storage system at a solar PV plant in Portugal, while power group EDP has added one to a hybrid wind and solar project in Spain.
July 31, 2026
The State Council of China recently released the 15th Five-Year Carbon Peaking Action Plan, outlining a roadmap for carbon peaking through the Action Plan period.