Tesla Powerwalls hooked up to provide grid frequency balancing in Vermont utility pilot

May 17, 2021
LinkedIn
Twitter
Reddit
Facebook
Email
Two Tesla Powerwalls

Green Mountain Power, a utility company in Vermont, has begun using Tesla Powerwall energy storage systems in customers’ homes as a frequency regulation resource to benefit the regional grid.

The company, which serves about 266,000 customers in the northeastern US state, was actually the first utility in the country to sell Tesla’s Powerwall residential systems after they were launched in 2015. As part of that offering, Green Mountain Power offered the chance to get a Powerwall at a discounted price or through a no-money-down subscription option if the ratepayer agreed to let the utility use some of the energy stored in the device to cut its peak demand.

In 2017, Tesla and Green Mountain Power rolled out a programme in partnership that would expand the virtual power plant (VPP) i.e. aggregated, capabilities of customers’ energy storage, offering Powerwalls for US$15 per month or US$1,500 upfront for 10 years. The programme partners would then use the batteries to provide grid services including dynamic capacity provision and for trading electricity in wholesale markets.

Last week, Green Mountain Power said customers that already have two Powerwalls installed through those previous schemes would be eligible to join its new pilot programme, through which aggregated storage systems will provide frequency regulation services to help maintain the reliability of the ISO New England grid. The utility said 200 customers have already enrolled.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

In exchange for US$13.50 per month back on their energy bills, plus some of the income from frequency regulation market participation paid by ISO New England, customers allow GMP to use their batteries. This can include rapid charging and discharging for periods of each month, but the utility said it will ensure customers have backup power available to them in case of forecasted extreme weather events that could affect their supply.

GMP was able to enter the frequency regulation market after a three month period of testing with the ISO and is doing so in partnership with Tesla, as well as with Customized Energy Solutions, a software company which GMP said provided key integrations between Tesla’s Powerwall hardware and Autobidder market optimisation and trading software and the grid operator’s network.

The scheme allows GMP’s existing network of Powerwall owners and subscribers to benefit from a further revenue stream while offering benefit and value to the utility and ISO New England. GMP said it plans to expand the pilot programme if successful.

Tesla’s Powerwalls — and energy storage systems from numerous other providers including rival Sonnen — have been used in frequency regulation applications before. In South Australia, a virtual power plant pilot was found to have earned significant income from just a handful of frequency correcting events in its first six months of operation. In early 2020 Tesla was seen showcasing the South Australia project at a trade event in Tokyo, Japan, with Japan expected to become more receptive to the concept as the country targets carbon emissions reduction to zero by 2050 and pursues a deregulated electricity market.

Incidentally, Swell Energy, a VPP project developer which uses Tesla Powerwalls as well as equipment from other manufacturers, recently expanded a programme with California utility Southern California Edison (SCE) to offer customers a second Powerwall device at discounted cost in return for allowing the battery systems’ participation as utility capacity services resources. Swell Energy CEO Suleman Khan said that customers conscious of the need to back up more than just their lights and a couple of other critcial loads are seeing the value in installing multiple battery units. The Powerwall’s latest incarnation, Powerwall 2, comes with 7kW rated output for peak charge and discharge and 13.5kWh capacity.

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!

Read Next

February 11, 2026
Energy storage developer NineDot Energy closes US$431 million in construction financing for New York BESS projects. Meanwhile, US energy efficiency and renewables company Ameresco completes multiple tax credit transfer and financing transactions for solar PV and BESS.
February 10, 2026
Energy storage developer and system integrator Energy Vault and sodium-ion battery energy storage system (BESS) startup Peak Energy have announced a 1.5GWh strategic development agreement.
February 10, 2026
South Korean battery and electronics materials manufacturer Samsung SDI and South Korean state-utility Korea East-West Power (EWP) have signed a memorandum of understanding (MOU) to develop and invest in global energy storage systems (ESS) and renewable energy projects.
Premium
February 9, 2026
Energy-Storage.news Premium speaks to Daniel Dedrick, US-based BESS developer and operator, GridStor’s CTO, about the company’s strategies for navigating FEOC and Section 301 tariffs.
February 9, 2026
Software-focused battery energy storage system (BESS) integrator FlexGen has put two utility-scale BESS projects in operation in Wisconsin and Iowa, US, totalling 700MWh.