Tesla Powerpack to enter UK’s FFR market with Open Energi technology

February 28, 2017
LinkedIn
Twitter
Reddit
Facebook
Email
The 500kWh Tesla Powerpack battery storage system is co-located with a solar farm and will tender to offer FFR services to National Grid next month. Image: Open Energi.

UK firm Open Energi’s Dynamic Demand technology has been integrated with Europe’s first grid-scale Tesla Powerpack installation in Somerset, UK, in preparation for the site entering the firm frequency response (FFR) tendering market.

The 500kWh battery storage system, which is co-located with a 500kWp solar farm, will be able to automatically store and discharge energy in response to electricity supply and demand across the UK.

Open Energi’s Dynamic Demand technology optimises the system’s operating profile to maximise revenue opportunities throughout the day, applying designed management techniques, while limiting the degradation of the battery lifetime.

The site is able to respond to changes in the grid within the 10 second demands of the FFR tender by National Grid, and has the capability to respond within one second if the site bids into future Enhanced Frequency Response (EFR) tenders.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

If successful in next month’s tender, an FFR contract with National Grid will allow the site to deliver new revenues for Camborne Energy Storage, which has a vested interest in the project. This is in addition to those taken from arbitrage whereby the Powerpack charges from the solar farm, or the grid during low pricing periods, and sells this into the market during peak demand periods.

David Hill, strategy director at Open Energi, said: “Energy storage is helping the UK transition to a smarter, cleaner energy system, but there’s more to unlocking value from it than putting a battery in a field.

“We’re using the latest machine learning techniques to manage battery performance in real-time. By understanding and managing state of charge in relation to fluctuations in solar PV generation and changes in electricity supply and demand we can maximise revenues and minimise wear and tear.”

source: Open Energi

The Somerset project is the first co-located energy storage project from CES, starting 2017 with around 50MW of consented sites ready for development.

Dan Taylor, managing director at CES, said: “We have ambitious deployment targets for energy storage in the UK and this successful project is an exciting step forward for us and the industry. It demonstrates the vital role of energy storage in delivering secure, low carbon power to the UK.

“We are aiming to co-locate further energy storage with renewable generation throughout the UK and help make our electricity system fit for the future.”

Speaking to Energy-Storage.News’ sister site Solar Power Portal about these future projects, Taylor explained that CES takes a technology-agnostic approach, meaning not all future sites are likely to feature more Tesla Powerpack systems.

Read Next

November 21, 2025
In a major week for European BESS deal-making, project acquisition and financing deals have been done in the Poland, Germany, Finland, the UK and Romania for grid-scale projects totalling well over 1GW of capacity.
November 20, 2025
From the US, Maxwell Technologies is acquired for its third time, by Clarios, Fullmark Energy completes a tax credit transfer, and OATI partners with Colville Tribes on microgrid solutions.
November 14, 2025
BESS and flexible generation provider Statera Energy has secured £235 million (US$309 million) in debt financing for its 680MW/1,360MWh Carrington BESS project in Manchester, UK.
November 13, 2025
Statkraft, Kyon Energy and Juniz Energy have progressed BESS projects in Germany, all in all totalling a combined 213MWh of capacity.
November 13, 2025
Octopus Australia has achieved financial close on a AU$900 million (US$587 million) DC-coupled hybrid facility that combines 300MW of solar generation with a 243MW/486MWh battery energy storage system (BESS) in New South Wales.