Centrica wants to aggregate 100 household battery systems into UK ‘Local Energy Market’ trial

LinkedIn
Twitter
Reddit
Facebook
Email

British-headquartered multinational utility Centrica will “most likely” install up to 100 residential energy storage batteries in selected homes in Cornwall in the south-west of England, alongside new installs of solar panels – if they are not already in place – as part of its local energy market (LEM) programme.

Speaking to our UK sister site Solar Power Portal this week, Sophie Orme, energy storage lead for the Cornwall LEM, said the project includes a residential workstream that has already attracted interest from 300 homes wishing to take part.

This will be whittled down in January when 150 on-site technical surveys will be conducted before around 100 are selected to take part. As Orme explained, a high number of homes in the region already have solar installed, with Centrica looking to conduct new installs for those without the technology.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Centrica has already identified hundreds of potential homes in the south west which could take part in the local energy market. Image: Centrica.

“A large proportion of the [respondents] already have solar PV, that’s the case in Cornwall in general as I think they are well engaged with new technologies and electricity prices. So about a third already have PV so for the two thirds who don’t we will be looking to install PV if their roofs are appropriate, and that’s part of the screening process,” she said.

In addition, energy storage and other smart grid applications will also be sought for the houses with Orme adding that it would be “most likely” that Centrica would install the units themselves.

“I can’t guarantee it but I suspect we will have a battery in all 100 homes,” she said before adding that a supplier had already been selected internally, although she was unable to name the company.

The goal of the project, as with the rest of Centrica’s activities in Cornwall, is to harness renewables and smart energy technologies to free up capacity on the local grid and provide flexibility to the distribution network operator or the national grid.

“With the residential [batteries] we’ll be looking at the fleet of residential sites and how with aggregation we might access some of those national and potentially local services,” Orme said.

It is not yet known if the battery supplier or Centrica itself will develop the aggregation platform to form the virtual power plant needed to provide these services. However Orme pointed to Centrica’s recent acquisition of European aggregator REstore as a potential source of the platform.

“There are some battery suppliers that we’ve looked at that do have that capability. We will need to look at how we interface with that. Centrica has also recently acquired an aggregator, the largest in Europe, and they have very good capability to do that.

“It’s to be confirmed how much we will do buying versus building, but they’ll be an element we’ll develop to interface,” she said.

Centrica has also just connected a 1MWh vanadium redox ‘flow machine’ energy storage system from provider RedT as part of the LEM trial.

2 June 2026
10am BST / 11am CEST
This webinar will provide a comprehensive overview of the current grid constraint landscape in Germany, with a focus on what it means in practice for the storage business case. Attendees will gain a clear understanding of how ramp rate restrictions and grid limitations translate into concrete business model challenges, with real-world examples illustrating how developers can structure tailored, constraint-aware models for a single project, including the multiple-scenario analyses increasingly required in Flexible Connection Agreement (FCA) processes. The session will then address the critical question of financing: how do route-to-market (RTM) players continue to assess and price battery projects in a constrained environment? And what do lenders actually need to see to get comfortable?
2 June 2026
Johannesburg, South Africa
RE+ South Africa is a premium platform for the commercial and industrial clean energy market, bringing together industry leaders for high-level education, networking, and business development opportunities. The event features a conference program focused on market insights and industry-shaping discussions alongside an exhibition showcasing solar, energy storage, microgrids, and other renewable energy technologies. Co-located with Securex South Africa, the event also fosters collaboration across sectors including safety, security, and facilities management that are critical to South Africa’s continued growth.
9 June 2026
Stuttgart, Germany
Held alongside The Battery Show Europe, Energy Storage Summit provides a focused platform to understand the policies, revenue models and deployment conditions shaping Germany’s utility-scale storage boom. With contributions from TSOs, banks, developers and optimisers, the Summit explores regulation, merchant strategies, financing, grid tariffs and project delivery in a market forecast to integrate 24GW of storage by 2037.
10 June 2026
3pm BST / 4pm CEST
As the energy transition accelerates, solar + BESS hybrid projects are rapidly becoming the new standard. But while many developers approach these systems with a “solar mindset,” battery storage introduces a fundamentally different layer of operational complexity, one that directly impacts performance, revenue, and long-term asset value. In this webinar, industry experts from Sonnedix and TWAICE will explore how to design and operate solar + BESS projects that are not only optimized for today’s requirements, but resilient and profitable in tomorrow’s markets.
23 June 2026
Munich, Germany
Every year, ees Europe, Europe’s largest and most international exhibition for batteries and energy storage systems, provides a networking opportunity for the industry’s key players – all under the motto “Innovating Energy Storage”. It focuses on the latest technologies, trends and market developments. ees Europe will take place from June 23–25, 2026 – for the first time running from Tuesday to Thursday – as part of The smarter E Europe at Messe München.
30 June 2026
Novotel London West, London, UK
The Clean Power Summit 2026 is the UK’s premier event for stakeholders driving the clean energy transition. As renewable capacity is forecast to nearly triple by 2035, this Summit offers a unique platform to shape the future of lowcarbon power, strengthen energy sovereignty, and unlock economic growth. Bringing together policymakers, developers, investors, network operators, and industry enablers, the Summit delivers actionable strategies to achieve the UK’s 2030 clean energy targets. With four dedicated content streams, attendees will gain exclusive insights into offshore wind expansion, floating wind innovation, regional manufacturing, and grid upgrades across the North Sea. This is your opportunity to connect with key decision-makers, explore investment opportunities, and collaborate on solutions to navigate complex supply chains and policy frameworks. The Clean Power Summit 2026 ensures stakeholders are equipped to turn ambition into action, driving progress and securing a sustainable energy future for the UK.

Read Next

May 27, 2026
The US can currently produce enough solar and battery energy storage system (BESS) modules to meet domestic demand, according to clean energy trade body American Clean Power (ACP).
May 27, 2026
Germany’s energy system regulator has confirmed that BESS projects coming online by 4 August 2029 will be exempt from charging and discharging grid fees, opening up investment again after months of uncertainty.
May 27, 2026
Solar Media Market Research analyst Charlotte Gisbourne looks at the changing revenue and margin dynamics in the BESS supplier landscape.
May 27, 2026
Adani Green Energy has commissioned over 3GWh of battery storage at the world’s largest single-location renewable energy project, in Khavda, Gujarat. 
May 27, 2026
MGA Thermal and Knode have commenced a Front-End Engineering and Design (FEED) study for a 195MWh electro-thermal energy storage project at Tronox’s Kwinana facility in Western Australia.