Battery with ‘maximum flexibility’ required for Indian mountain state tender

LinkedIn
Twitter
Reddit
Facebook
Email
The battery and solar project will be located in the mountainous state of Himachal Pradesh, facing huge temperature variations. Flickr: Simon

Solar Energy Corporation of India (SECI) has issued a tender for EPC of a grid-connected 2MWac solar PV project linked with 1MW / 1MWh of battery energy storage on government land at Kaza, in the mountainous state of Himachal Pradesh.

The notice of issue (NIT) was released on behalf of Himachal Renewable Limited, a JV between SECI – which was itself established by the Ministry of New and Renewable Energy (MNRE) – and Himachal Pradesh State Electricity Board (HPSEBL).

The tender is for design, engineering, supply, construction, erection, testing, commissioning including five of O&M services of the plants at the town of Kaza, which is the subdivisional headquarters of the remote Spiti Valley in the Lahaul and Spiti district.

The battery will be located at Rangreek, near Rong Tong Hydro Power Station, 12,000 feet in altitude, facing annual temperature ranges of -40°C to 30°C. The area can see snow of up to six feet in winter months.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The tender noted that the battery “shall be designed for maximum flexibility with regard to site-specific voltages, frequency, phase imbalance, and protection requirements”.

Any battery technology can be used as long it is deemed suitable for the location’s climatic conditions. The batteries will also be containerised.

There was good news for energy storage in India recently with the reduction of the Goods and Service Tax (GST) on lithium-ion batteries.

SECI also recently issued a tender for two 1.5MW(AC) solar power projects with battery energy storage systems of 0.75MW / 2.5MWh each at two locations in the state of Jammu and Kashmir.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

October 2, 2026
India’s Union Cabinet has approved US$ 19.3 billion Green Energy Corridor, including US$ 5.2 billion for 50GWh BESS through FY2032-33.
October 2, 2026
Outgoing California Governor Gavin Newsom recenty addressed approximately 1,200 bills, including several energy storage and solar related bills that were either approved or vetoed.
October 1, 2026
Maharashtra’s electricity regulator has proposed mandatory BESS for renewable projects seeking grid connectivity.
September 30, 2026
IPP Northland Power has announced that its 80MW/160MWh Jurassic energy storage project in Cypress County, Alberta, CA, has achieved commercial operations.
September 30, 2026
Kerala has proposed a five-year tariff framework with rules for BESS, PSP, including efficiency, availability and grid-forming requirements.