The battery and solar project will be located in the mountainous state of Himachal Pradesh, facing huge temperature variations. Flickr: Simon

Solar Energy Corporation of India (SECI) has issued a tender for EPC of a grid-connected 2MWac solar PV project linked with 1MW / 1MWh of battery energy storage on government land at Kaza, in the mountainous state of Himachal Pradesh.

The notice of issue (NIT) was released on behalf of Himachal Renewable Limited, a JV between SECI – which was itself established by the Ministry of New and Renewable Energy (MNRE) – and Himachal Pradesh State Electricity Board (HPSEBL).

The tender is for design, engineering, supply, construction, erection, testing, commissioning including five of O&M services of the plants at the town of Kaza, which is the subdivisional headquarters of the remote Spiti Valley in the Lahaul and Spiti district.

The battery will be located at Rangreek, near Rong Tong Hydro Power Station, 12,000 feet in altitude, facing annual temperature ranges of -40°C to 30°C. The area can see snow of up to six feet in winter months.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The tender noted that the battery “shall be designed for maximum flexibility with regard to site-specific voltages, frequency, phase imbalance, and protection requirements”.

Any battery technology can be used as long it is deemed suitable for the location’s climatic conditions. The batteries will also be containerised.

There was good news for energy storage in India recently with the reduction of the Goods and Service Tax (GST) on lithium-ion batteries.

SECI also recently issued a tender for two 1.5MW(AC) solar power projects with battery energy storage systems of 0.75MW / 2.5MWh each at two locations in the state of Jammu and Kashmir.

Read Next

April 21, 2026
Danish investment firm Copenhagen Infrastructure Partners (CIP) has begun construction on the 300MW/1,500MWh Patache battery energy storage system (BESS) in northern Chile.
April 20, 2026
In this US news roundup, Eos and Turbine-X, CPower and Vertiv, and Elevate Renewables highlight the ‘bring your own capacity’ model in data centre-focused announcements.
April 15, 2026
Thermal management means cost, complexity and aux power consumption for battery storage projects, writes William Lauwers of Enertis Applus+.
Premium
April 14, 2026
Over 1.4GW/3.4GWh of grid-scale BESS came online in Europe, likely its best month ever, accounting for almost a fifth of global figures.
April 9, 2026
The recent European Union-India agreement could unlock innovation and scale in energy storage, writes Eugene Beh, CEO of Quino Energy.