New York awards 159MW of co-located BESS in 2.4GW renewable tender

June 13, 2022
LinkedIn
Twitter
Reddit
Facebook
Email

New York has awarded 22 solar PV projects totalling 2.4GW of power, including six co-located sites with a combined 159MW of battery energy storage systems (BESS).

The awards represent the state’s largest land-based procurement of renewable energy to-date, first covered by Energy-Storage.news‘ sister site PV Tech. The 22 projects will require US$2.7 billion in investment and some or all should be online by 2025.

Winning co-located projects from developers EDF Renewables (three) and Boralex (one) account for 85% of the 159MW of awarded BESS capacity, with ReneSola Power and Northland Power also adding storage onto their winning solar projects.

EDF Renewables, part of the global French state-owned energy group, will deliver three sites with 20MW of BESS each: Columbia Solar Energy Center in Herkimer County, Ridge View Solar Energy Center in Niagara County and Rich Road Solar Energy Center in St. Lawrence County.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Columbia and Ridge View are also the largest winning solar projects by power, with 350MWac each, and Rich Road’s 250MWac brings EDF’s total contribution to 950MW, 40% of the 2,408MW awarded.

Boralex is pairing its 250MW Fort Covington Solar Farm with a 77MW/308MWh (four hours) BESS, in Suffolk County, while its four other winning projects are standalone solar: all five total 540MW of solar power.

EDF has not revealed the duration/MWh of its three BESS projects. Though this varies greatly in the state of New York, it may be trending towards four hours with Boralex’s winning tender and a Summit Ridge project announced last week both opting for it. And in April, the New York Power Authority (NYPA) began a process of adapting fossil fuel sites to be replaced with four-hour BESS units.

Rounding off the winning co-located projects, Northland Power is adding 20MW of storage to its 100MW Alfred Oaks Solar project in Allegany county, while ReneSola Power is pairing its 19.99MW Roosevelt Solar project in St. Larwence with 2MW of storage.

“Today’s investments will put us on a path to making New York a greener place to live while also creating new jobs and spurring economic development,” governor Kathy Hochul said. “These projects will allow us to not just meet but exceed our goal of obtaining 70 percent of our electricity from renewable resources (by 2030) and will further cement New York as a national leader in the fight against climate change.”

The contracts for the 22 projects include an index REC (renewable energy certificate) structure which will help cushion electricity consumers in the state against spikes in energy prices. The weighted-average all-in development cost of the projects amounts to $63.08 per megawatt-hour.

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

February 20, 2026
A flurry of BESS project news from big-name players in Western Europe in the run-up to the Energy Storage Summit next week, with Neoen, Statkraft, Zenobē and Infranode moving projects forward in Germany, Ireland, the UK and Denmark. Highlights include a 15-year toll between Drax and Zenobē, and multiple 4-hour duration systems.
February 19, 2026
In this US news roundup, CC Power signs an agreement with Hydrostor for 400MWh of its Willow Rock LDES project, PowerSecure builds microgrids in New Mexico, and ESS Inc acquires VoltStorage.
Premium
February 19, 2026
“Australia remains a multi-gigawatt proving ground for utility-scale energy storage systems,” says Kashish Shah of Wärtsilä Energy Storage.
February 18, 2026
IPP Lydian Energy has secured US$689 million in financing for two solar projects and a battery energy storage system (BESS) project in New Mexico, Texas, and Utah, US.
February 18, 2026
The US Treasury’s interim FEOC guidance has outlined “Material Assistance” provisions, which rely heavily on existing safe harbour calculations.