Mexico’s 190MW co-located battery storage project ‘good news’ for sector

LinkedIn
Twitter
Reddit
Facebook
Email

A state-owned solar-plus-storage project being developed in Mexico firmly establishes the shift in government thinking on energy storage, a local battery storage firm told Energy-Storage.news.

The Ministry of Environment and Natural Resources (Semarnat) last week conditionally authorised the construction of a transmission line for the Puerto Peñasco Photovoltaic Power Plant, a megaproject combining 1GW of solar PV and 190MW of battery energy storage.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The project in the state of Sonora was first proposed by the Federal Electricity Commission (Comision Federal de Electricidad or CFE) in late 2021 but has moved forward in the last few months. The solar PV will be built in four stages with completion due by 2028.

The total investment required has been reported at around US$1.6 billion, or 33 billion Pesos, with ownership to be split 54:46 between the federal government and the state of Sonora.

Alejandro Fajer, managing director of Mexico City-based battery storage system integrator Quartux, said it is the first energy storage project by the current government and a massive turning point for the country’s grid-scale market.

“This is good news. The project establishes the government’s shift towards saying that energy storage is something it can trust and is very interested in. Given all the analysis, energy storage is one of the best solutions for our grid intermittency problems,” he said.

“The energy storage system will also be interacting with the open electricity market, which is something unheard of.”

According to a technical document from the CFE from 2021, the first stage of the project involves 120MW of PV with 10MW/20MWh of energy storage while stage two would add another 200MW of PV and 60MW/120MWh of energy storage. It did not provide figures for the third and fourth stages.

The project will provide power to the states of Sonora and Baja California.

The energy storage market in Mexico has to-date been mainly focused on smaller projects in the commercial & industrial (C&I) sector. Companies like Quartux and On.Energy help businesses and industrial sites reduce electricity costs through peak shaving and self-consumption while also improving energy security in less-well serviced parts of the country’s electricity grid.

Energy-Storage.news’ publisher Solar Media will host the 5th Energy Storage Summit USA, 28-29 March 2023 in Austin, Texas. Featuring a packed programme of panels, presentations and fireside chats from industry leaders focusing on accelerating the market for energy storage across the country. For more information, go to the website.

Read Next

March 27, 2024
Developer Better Energy is deploying its first battery energy storage system (BESS), a 10MW/12MWh system, at one of its solar PV plants in Denmark.
Premium
March 26, 2024
The issue of ensuring reliability of BESS resources in the Texas electricity market has not gone away for grid operator ERCOT, despite the state regulator’s recent quashing of proposed minimum state-of-charge (SOC) rules.
March 26, 2024
UK-based energy company Statera Energy has secured planning consent for a 290MW/1,740MWh battery energy storage system (BESS) to be developed in Southwest England.
March 25, 2024
Primergy has signed a “long-term” power purchase agreement (PPA) with California community energy supplier San Diego Community Power (SDCP).
March 25, 2024
The Australian Renewable Energy Agency (ARENA) is funding trial deployments of two different non-lithium battery technologies at microgrids in Western Australia.

Most Popular

Email Newsletter