Local authority in England approves plan for 50MW PV farm with 50MWh battery option

March 1, 2018
LinkedIn
Twitter
Reddit
Facebook
Email
An existing solar PV farm in the UK. Image: Lightsource.

North Kesteven District Council, a local authority in England’s Midlands, has approved a near 50MW solar farm alongside planning consent for a 50MWh battery for Pegasus Group, adjacent to an existing 18MW solar farm.

Plans for the Branston Solar Extension were approved last week, which will see the 49.9MW project – with a 40MW export capacity – delivered on land near to the Branston potato processing and preparation facility outside Lincoln, which is north-east of Nottingham in England’s East Midlands region.

The potential 25MW/50MWh battery is not provided for by the approved grid connection and so Pegasus Group will now engage with local distribution network operator Western Power Distribution to see the storage facility utilised.

There is a small import capacity within the existing grid offer and so discussions with WPD will seek to see this increased.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

A spokesperson for the applications added that the company would seek outside parties to build the business case for the battery.

Josh Pollock of Pollock Associates also told our UK sister site Solar Power Portal there is potential for up to 10% of the generation from the solar park to be utilised through a hardwire power purchase agreement with the nearby potato processing company.

Pegasus Group says it was able to secure planning officer recommendation for the site without any objections after working closely with councillors and planning officers while consultation with the local community.

Emma Ridley, a planner with Pegasus Group, said: “To receive planning approval with no objections reflects not only the viability of the scheme and suitability of the site, but also the depth of work carried out in respect of community consultation.”

In a recent market research report, Solar Media analyst Lauren Cook forecast ‘explosive growth’ for UK battery energy storage projects through to 2022, including a growing case for co-location or pairing with renewable generation.

15 April 2026
Milan Marriott Hotel, Italy
Solarplus Europe 2026 marks the evolution of Europe’s longest-running solar conference, reflecting the industry’s transition from standalone PV to fully integrated solar-plus-storage and hybrid energy systems. Taking place in Milan, the Summit will unite developers, investors, policymakers, and technology leaders to explore how Europe can deliver firm, flexible, and bankable renewable power at scale. With a sharp focus on system integration, storage deployment, hybrid project design, and market-ready business models, Solarplus Europe provides the platform for shaping the next phase of the continent’s solar and clean power build-out.
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

Premium
April 8, 2026
A panel at the 2026 US Energy Storage Summit in Dallas, Texas, discussed the “creative, innovative structures” developers are having to embrace to secure long-term revenues for energy storage projects.
April 8, 2026
The Canadian Province of Prince Edward Island’s PEI Energy Corporation (PEIEC) has issued a request for expressions of interest (REOI) for a 10-50MW, four-hour duration battery energy storage system (BESS).
April 8, 2026
IPPs Zelestra, BNZ and ALFI have secured offtake and financing to hybridise solar projects with BESS across Spain, Italy, Portugal and Romania. 
April 7, 2026
Quebec-based IPP Boralex and Six Nations of the Grand River Development Corporation (SNGRDC) have announced the closing of a CA$202 million (US$145.12 million) financing for a 125MW/500MWh battery energy storage system (BESS) in Oxford County, Ontario, CA.
Premium
April 7, 2026
The project represents a US$128.6 million investment and is scheduled to begin construction this year, with commercial operations commencing in December 2026.