Iowa regulator approves solar-plus-storage project with 50MW BESS

April 26, 2023
LinkedIn
Twitter
Reddit
Facebook
Email

The Iowa Utilities Board (IUB) has given the green light to a solar and storage project from National Grid Renewables, with a 50MW battery energy storage system (BESS).

The IUB last week (21 April) granted an electric generating certificate and an order granting a request for waivers and a certificate of public convenience, use and necessity to the Grand Junction Solar project.

The solar-plus-storage project in Greene County pairs 100MW of solar PV a 50MW BESS. The BESS will optimise the solar PV array, storing electricity generated by the solar panels when it is abundant and discharging it to the grid when most needed. It did not reveal the discharge duration of the BESS unit.

The project is being developed by National Grid Renewables, part of the UK grid operator National Grid. It will cover approximately 1,103 acres of which four acres will be for the BESS. It will connect to the grid, operated by independent system operator MISO, via a generation-tie line extending to the Karma substation.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The order from the IUB requires Grand Junction to seek IUB approval for either an enlargement or transfer of ownership of the project to another entity. It also grants Grand Junction’s request to waive a public evidentiary hearing and associated procedural requirements under Iowa law.

Grand Junction Solar will need to file final design plans and evidence of having obtained all city and county permits to the IUB before construction starts. If it doesn’t complete the project within the two years after a final permit is issued it needs to file an a new application.

The IUB similarly granted certificates of use to a solar-plus-storage project from NextEra in August last year, with a 300MWh of co-located BESS.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

April 28, 2026
Utility DTE Energy has said it will forego customer rate increases for two years dependent on the success of a US$16 billion data centre campus involving a battery energy storage system (BESS).
April 28, 2026
IPP Grenergy has entered into a long-term toll with an ‘investment grade’ international utility for a solar PV co-located BESS of 680MWh in Spain.
April 28, 2026
Sumitomo Electric will supply a vanadium redox flow battery (VRFB) energy storage system to enable grid integration of wind energy in Hokkaido, northern Japan.
April 28, 2026
Australian infrastructure contractor GenusPlus Group has been awarded an AU$110 million (US$78.5 million) engineering, procurement, construction and commissioning contract for the 200MW/800MWh Koolunga battery energy storage system (BESS) in South Australia.
April 28, 2026
ARENA is supporting two First Nations-led microgrid projects in the Northern Territory (NT) with AU$11 million in funding.