India’s hybrid solar-wind-storage projects take shape with tenders and innovative steps forward

December 12, 2017
LinkedIn
Twitter
Reddit
Facebook
Email
Dr Harikumar Ramadas, director of ANERT and G. Sivaramakrishnan, joint secretary, KREEPA, at Intersolar India 2017. Credit: KREEPA/ANERT

Plans are in place for a combined 160MW solar and wind project with up to 40MWh of energy storage in the Indian state of Andhra Pradesh, while a smaller scale demonstration project experimenting with multiple technologies is being developed for Kerala.

Bharat Reddy, deputy general manager, Solar Energy Corporation of India (SECI), told PV Tech that AP Solar Energy Corporation, AP Nedcap and APTransco are planning to tender a project involving 120MW of solar, 40MW of wind and 20-40MWh of storage by March next year. The storage element will be technology agnostic.

SECI is providing some investment with backing from the World Bank and the plant will be located inside a new solar park in Anantpur in Andhra Pradesh. This will be the largest such system in India.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Kerala’s demo project up for tender

Elsewhere, a tender for a large-scale, hybrid solar-wind-storage demonstration project in the Indian state of Kerala is due to be issued with one month, according the state nodal agency for the Ministry of New and Renewable Energy.

Speaking to our sister site PV Tech at Intersolar India 2017, Dr Harikumar Ramadas, director of the Agency for Non-Conventional Energy and Rural Technology (ANERT), said the technology demo would be located at Ramakkalmedu, including 3MW of solar, 4MW of wind, and battery storage.

Deliberately situated in a tourist zone, there are plans to launch a training centre on site, allowing the public to view the system and witness the performance evaluations and studies.

Ramadas said ANERT has already secured 40 hectares of land and a tender for project development is expected to be floated in the next month. The project, expected to require INR160 million (U$2.4 million) investment, already has administrative sanction from the government for its first phase. The whole programme is envisioned to take 2.5 to 3 years.

Rewarding innovation

Ramadas said the inverters will have an “indigenous” design from CDAC. Then Trivandrum-based Kerala government-affiliated electronics manufacturer KELTRON will be fabricating the inverter designed by CDAC.

Meanwhile, polycrystalline modules will be allocated to 2MW of the system, and 1MW will be divided into different categories of amorphous and monocrystalline module architectures.

Furthermore, an array of different module technologies will be deployed across 100kW with trackers and then again across 100kW without trackers.

On the energy storage front, ANERT will be collaborating with CECRI and most of the system will use lithium-ion batteries, with the rest dedicated to sodium sulphide (NAS), and then lithium ferro phosphate if possible.

ANERT in partnership with Kerala Renewable Energy Entrepreneurs and Promoters Association (KREEPA) will also be heading outside India to the Middle East next year to launch an investor meeting, where both organisations will campaign for investment from non-resident Indians.

G. Sivaramakrishnan, joint secretary, Kerala Renewable Energy Entrepreneurs and Promoters Association (KREEPA) said there is a huge amount of water bodies in the state, which can be used for floating solar. Pilot projects are under way, with a couple of projects are already delivered including at Wayanad.

Among others, the major initiatives of ANERT include installation of solar power plants in government buildings, arrangements with local self-governments for providing subsidy to those in need. It will also look to partner cooperative banks for providing financial support to install renewable energy systems and to give Viability Gap Funding (VGF) for innovative projects on a megawatt-scale undertaken by State public sector undertakings (PSUs).

Read Next

November 26, 2025
Potentia Energy has received federal environmental approval for its 1,000MWh Tallawang Solar Hybrid project, and Fluence has delivered its Gridstack battery energy storage equipment to Ampyr Australia’s 600MWh Bulabul Battery installation.
November 19, 2025
Solar Energy Corporation of India (SECI) has agreed on BESS and hybrid solar developments with the Government of Andhra Pradesh.
November 13, 2025
Statkraft, Kyon Energy and Juniz Energy have progressed BESS projects in Germany, all in all totalling a combined 213MWh of capacity.
November 13, 2025
Octopus Australia has achieved financial close on a AU$900 million (US$587 million) DC-coupled hybrid facility that combines 300MW of solar generation with a 243MW/486MWh battery energy storage system (BESS) in New South Wales.
November 12, 2025
India’s Adani Group has made its first entry into the battery storage market, announcing a ‘flagship deployment’ that will be the country’s largest project so far when completed.