Government fast track towards construction for two pumped hydro projects in India

August 5, 2024
LinkedIn
Twitter
Reddit
Facebook
Email

The Central Electricity Authority of India (CEA) is fast-tracking two large-scale pumped hydro energy storage (PHES) projects totalling 2,600MW of power.

In an announcement on Friday (2 August), the CEA said it has ‘accorded concurrence’ to the two proposed long-duration energy storage (LDES) facilities, which are both being developed by state government-owned entities.

This, the authority said, is in order to enable their commissioning “on a fast track”. The announcement comes shortly after the government’s finance minister Nirmala Sitharaman pledged in the Union Budget 2024 that PHES plants would be supported by policy measures.

The CEA advises the Indian government on policy and formulates electricity system plans. As regular readers of Energy-Storage.news may have seen, its National Electricity Plan 2023 which helps guide the Ministry of Power called for large deployments of both battery energy storage system (BESS) and PHES-based energy storage in the coming years.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

As India targets 500GW of new non-fossil fuel energy by 2030, and net zero emissions from all sectors of the economy by 2070, the integration of storage into the power system will become increasingly vital, the CEA and government have projected.

By the 2031-2032 timeframe, that equates to about 47GW/236GWh of grid-connected batteries, and 27GW/175GWh of pumped hydro, for a total 74GW energy storage output and 411GWh capacity.

By 2047, CEA modelled that a total of 320GW/2,380GWh will be needed, with 230GW/1,840GWh from battery storage and 90GW/540GWh from PHES.

176GW of pumped hydro potential across India

CEA said that it has so far received around 60GW of proposals for PHES projects, currently at the Survey & Investigation stage, ahead of detailed project reports (DRPs) being put together.

The two projects selected last week are the 600MW Upper Indravati PHES in Odisha, being developed by Odisha Hydro Power Corporation (OHPC), and the 2000MW Sharavathy project in Karnataka, in development through Karnataka Power Corporation Ltd (KPCL).

Upper Indravati would see pumped hydro capacity added to an existing 600MW (4 x 150MW unit) hydroelectric power plant. According to OHPC’s website, the corporation also wants to add pumped hydro to two other operational hydro plants, the 320MW Upper Kolab plant and 510MW Balimela plant.

Sharavathy meanwhile appears to be a 2,000MW PHES addition to an existing 1,035MW pumped hydro plant in Karnataka.

In addition to fast-tracking the two plants towards DRP status, the CEA has revised its guidelines for submitting projects into planning, which again is aimed at streamlining and speeding up the process.

CEA noted that in addition to the 60GW of submitted proposals, India currently has 4.7GW of PHES plants in operation, 4GW already under construction and 3.6GW have ‘concurred,’ meaning construction is to be started. India’s total PHES, or pumped storage plant (PSP) potential, to use CEA’s own terminology, is about 176GW, the authority said.  

See more of Energy-Storage.news’ coverage of the energy storage sector in India, including recent tenders for standalone energy storage, renewables-plus-storage and Firm Dispatchable Renewable Energy FDRE.

Read Next

January 9, 2026
Mukesh Chatter, CEO of US sodium-ion battery startup Alsym, on the prospects for non-lithium alternative technologies in 2026 and beyond.
January 8, 2026
Giriraj Rathore, senior director of global business development at Hithium, discusses market and technology development dynamics as part of our annual Q&A series.
January 8, 2026
Australia-based battery technology firm Altech Batteries has received a binding conditional funding approval for a sodium-chloride solid-state battery manufacturing facility in Germany.
January 8, 2026
Four projects have been selected in Peninsular Malaysia’s first programme to build large-scale battery energy storage system (BESS) facilities.
January 7, 2026
Western Australia has launched the fourth round of its Clean Energy Innovation Grants programme, prioritising long-duration energy storage.