Enel brings 555MWh of BESS online in ERCOT

LinkedIn
Twitter
Reddit
Facebook
Email

Enel North America has brought five battery energy storage system (BESS) projects online in ERCOT, Texas, totalling 369MW/555MWh of energy storage.

The company, part of Enel, the large Italy-headquartered utility and independent power producer (IPP), brought the projects online over the course of summer. This brings Enel North America’s operational utility scale BESS capacity to 520MW/780MWh and the company expects to bring another 823MW/1,234MWh online over the next year.

Two are 59MW/89MWh in size, another two are 57MW/86MWh and the fifth is a 137MW/206MWh system. All are co-located with parts of Enel’s existing renewable energy portfolio in the state and have a discharge duration of 1.5 hours, notably lower than the two-hour standard seen in most projects in Texas today.

The company already has 3.3GW of solar and wind capacity operational in the Lone Star State and recently launched a retail energy business there. Enel said the utility-scale BESS projects participate in Texas’ ancillary services, run by grid operator ERCOT.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The main ancillary services ERCOT runs are Reg-Up and Reg-Down, Responsive Reserve Service (RRS or spinning reserve) and non-spinning reserve. Reg-Up and Reg-Down are frequency regulation services of which help keep the grid at 60hz by balancing fluctuations within the energy market’s five-minute intervals, while RRS is the provision of capacity used in case a generating unit trips offline.

ERCOT declared an Energy Emergency Level 2 alert on Wednesday last week (6 September) when reserves were running low. In response, Enel delivered 524MWh of energy from its seven BESS units in the state while its renewable portfolio in the state generated 19.9GWh of energy through the day. It also utilised 145MW of its 200MW demand response portfolio to help the operator balance the grid.

“With extreme heat propelling Texas’ energy demand to record-breaking levels, the addition of these five new battery storage systems couldn’t have come at a better time,” said Paolo Romanacci, head of Enel North America’s renewable energy business, Enel Green Power North America.

The state looks set to reach 9.5GW of grid-scale BESS online by October next year as developers and IPPs capitalise on ancillary service and energy trading opportunities, with the ERCOT electricity market having amongst the highest market spreads in the world. Around 3.3GW was online as of June this year according to ERCOT’s figures.

In Italy, its home market, Enel is also one of the most active in deploying projects in the country’s burgeoning grid-scale energy storage market, with the largest portfolio of under-construction units in the country launched earlier this year.

Our publisher Solar Media is hosting the 10th Solar and Storage Finance USA conference, 7-8 November 2023 at the New Yorker Hotel, New York. Topics ranging from the Inflation Reduction Act to optimising asset revenues, the financing landscape in 2023 and much more will be discussed. See the official site for more details.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

June 10, 2026
EDP and SRP complete 200MW/800MWh Arizona BESS, Pathway Power closes $150m facility, and B2U secures Waymo supply deal for second-life EV batteries in grid storage.
Premium
June 9, 2026
ESN Premium speaks with Dr Thomas Sisto, of flow battery developer XL Batteries, about using LDES to combat grid strain from heatwaves and data centres.
June 8, 2026
California-headquartered developer esVolta has closed an expanded corporate credit facility providing up to US$450 million of capital to expand new utility-scale energy storage projects in the US.
June 5, 2026
Developer EDF power solutions North America and developer-operator Abu Dhabi Future Energy Company – Masdar, have entered into 15-year power purchase agreements (PPAs) for a California, US solar-plus-storage project.
June 5, 2026
Virtual power plant (VPP) operator and distributed energy resource (DER) platform Voltus and tech giant Google have signed a three-year 100MW agreement for the PJM region in the US.