EC-funded study progresses battery storage hybridisation of pumped hydro plant in Slovakia

August 28, 2025
LinkedIn
Twitter
Reddit
Facebook
Email

European Commission (EC) funding is supporting a project to integrate battery storage at a pumped hydro energy storage (PHES) plant in Slovakia.

The European Union (EU) executive and legislative arm highlighted this week (25 August) that €2.1 million (US$2.44 million) funding is being used for the project, which assesses how best to hybridise the 735MW Cierny Vah PHES plant with a battery energy storage system (BESS) and modernise two of the facility’s six units.

The effort is being funded through the Connecting Europe Facility (CEF) for Energy, the EU programme to implement Trans-European Networks for Energy policy. It aims to support investments in new cross-border energy infrastructure and upgrades to existing infrastructure.

‘Modernisation of Pumped Hydroelectric Energy Storage in Cierny Vah’ was designated a Project of Common Interest (PCI).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

It began in October 2024, coordinated by Slovenske Elektrarne, Slovakia’s biggest electricity utility. The state owns 34% of Slovenske Elektrarne, and Slovak Power Holdings, a joint venture between Czech power company EPH and Italy-headquartered Enel, owns the remaining 66%. However, EPH is expected to buy out Enel’s share during this year.

The EC said this week that over the next two years, preparation will be made for converting two pumped turbine units to variable-speed turbines, which will improve Cierny Vah’s operational efficiency.

At the same time, the optimal configuration and design integration for a BESS of up to 80MW/160MWh will be studied. These studies are expected to define technical specifications for hybridising the PHES plant, from market simulations and financial assessments to detailed technical design of components and control systems.

Slovenske Elektrarne has called the project SE Integrator, noting that the need for it arises from the growing share of variable renewable energy (VRE) on the grid. This results in short-term fluctuations, which batteries can help solve, as well as longer-term mismatches between renewable production and grid demand, e.g., daytime solar vs the evening peak.

The project will enter the Final Investment Decision (FID) phase upon the conclusion of the EC-funded studies. The European Commission said that in addition to balancing the Slovakian grid, balancing energy could be exported and traded with neighbouring countries such as Hungary, Poland, and the Czech Republic.

Various projects involving the hybrid integration of batteries to run-of-river hydroelectric generation facilities have been carried out, are ongoing or are planned around the world, including projects in the Philippines, Bulgaria, Germany and other regions.

The direct pairing of long-duration energy storage (LDES) pumped hydro with battery storage appears to be a much rarer concept so far, although developers SENS and Callio in Finland announced a project early last year which would combine the two, along with solar PV generation at a decommissioned mine.     

6 October 2026
Warsaw, Poland
The Energy Storage Summit Central Eastern Europe is set to return in September 2025 for its third edition, focusing on regional markets and the unique opportunities they present. This event will bring together key stakeholders from across the region to explore the latest trends in energy storage, with a focus on the increasing integration of energy storage into regional grids, evolving government policies, and the growing need for energy security.

Read Next

February 17, 2026
Australian Vanadium Limited has secured an exclusive partnership with Sumitomo Electric Industries for the 500MWh Kalgoorlie vanadium BESS.
Premium
February 12, 2026
Thimo Mueller of ASL discusses the recent 12GWh LDES tender in New South Wales, Australia, with ESN Premium.
February 11, 2026
Netherlands-based iron-air long-duration energy storage (LDES) startup Ore Energy has completed a grid-connected pilot of its 100-hour iron-air LDES system at EDF Lab les Renardières in France.
Premium
February 11, 2026
Owner-operator Fidra Energy came out of virtually nowhere to be building one of Europe’s largest BESS in the UK, the 1.4GW/3.1GWh Thorpe Marsh project. We catch up with CEO Chris Elder, about its strategy and projects but also broader BESS and clean energy financing trends.
February 6, 2026
NSW concludes Australia’s largest LDES tender, awarding six battery projects 12GWh. Industry calls it “game-changer” for grid reliability.