Bulgaria’s NEK deploying BESS at hydropower plants

LinkedIn
Twitter
Reddit
Facebook
Email

State-owned utility and power generation firm NEK is deploying BESS at its hydropower plants across Bulgaria.

The National Electricity Company (NEK) is moving to upgrade five hydropower plants with battery energy storage system (BESS) technology according to local reports, partially confirmed by announcements on NEK’s website.

The company aims to add a 10MWh BESS unit to its new Vacha 1 hydropower plant by the end of 2025 and has launched a call to do the same at four others. Those four have a total expense cited by reports of €63.2 million (US$65 million).

On 20 January, NEK announced four separate notification of investment intentions for energy storage systems, in the towns of Boynik, Aleko Konstantinov, Muhovo and Devin in the Kardzhali, Pazardzhik, Sofia and Smolyan regions respectively. Those locations are in the south and west of Bulgaria.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The announcements didn’t give more information than that, but local reports said the four additional BESS units will total ‘at least’ 279MWh.

The reports indicate the hydropower plants are run-of-river, while NEK also has substantial pumped hydro energy storage (PHES) plants both operating and in construction across Bulgaria.

The BESS will help to optimise the production of the five hydropower plants, and will be deployed with configurations of between two and three hours and capable of at least 6,000 cycles. The four additional hydropower plants to have co-located BESS are Studen Kladenets, Aleko, Devin and Topolnitsa, the reports add.

Bulgaria was in the headlines late last year after a 3GWh standalone energy storage tender, funded by the EU’s Recovery and Resilience programme, was oversubscribed by a factor of four.

The largest grid-scale BESS projects online that Energy-Storage.news has reported on are a 55MWh project by independent power producer (IPP) Renalfa and a 17.8MWh commissioned by China-based energy storage technology firm Sermatec for an unnamed owner.

2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.

Read Next

November 20, 2026
Large-scale BESS projects in Germany have been progressed towards construction by Elements Green, Voltwise, EnBW, Green Flexibility, Flower and Dispatch totalling over 4GWh of capacity.
November 19, 2026
BW ESS has partnered with Lyon-based developer Wattmen to develop around 500MW of BESS projects in France over the next three years.
November 19, 2026
Statkraft has signed a 10-year deal with Ampyr Solar Europe covering the Snelle Loop co-located solar PV and BESS project in the Netherlands.
November 12, 2026
Stadtwerke Gaggenau, a municipal utility in Germany, has hired a general contractor to build a 4-hour BESS project using the zinc-bromide technology from US firm Eos Energy Enterprises.
November 11, 2026
Envision Energy will supply its Gen 8 BESS platform for ju:niz Energy’s 442MWh Smareg 13 project in Bavaria, Germany.