€20m grant funding for Namibia’s first grid-scale BESS from Germany’s national development bank

LinkedIn
Twitter
Reddit
Facebook
Email
NamPower managing director Kahenge S Haulofu, National Planning Commission director general Obeth Kandjoze and KfW’s Barbara Pirich at a signing ceremony earlier this month. Image: NamPower via LinkedIn.

A grant of €20 million (US$22.66 million) has been made to Namibia’s government-owned electric utility company for the development of the African country’s first grid-scale battery storage project. 

Namibia Power Corporation (NamPower) told Energy-Storage.news that through a bilateral cooperation agreement between the federal German government and the Republic of Namibia, Germany’s KfW development bank has made the funding available. 

It will go towards the construction of a 58MW / 72MWh battery energy storage system (BESS) at Omburu substation in Namibia’s western Erongo region. 

It will perform a number of applications for NamPower: peak load shifting, energy arbitrage, emergency back up power provision, ramp-rate control of power plants and reactive power control. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

NamPower will contribute around 20% of the total project costs, paying for transmission interconnection and local duties and taxes not covered by the grant funding. 

The Omburu BESS will contribute to the expansion of renewable energy in the region by storing locally generated renewable power as well as electricity imported from the Southern African Power Pool (SAPP), which can charge the battery at cheaper, off-peak times, and then the energy can be discharged during peak times. 

This would also offset the use of energy from the 120MW Van Eck Power Station, Namibia’s only coal-fired power plant, which as the utility pointed out is now ageing, having been built in the early 1970s. 

The BESS will also be used to load-follow local renewable energy generation, helping to stabilise the grid as it accepts the variable output of solar or wind plants. 

Finally, it will also enable Namibia to increase its participation in energy trading with the 11 other member states of the SAPP, helping to lower overall emissions across the pool. 

Namibia has a National Energy Policy target of sourcing 80% of its energy from local sources by 2023 and a Renewable Energy Policy target of 70% by 2030. The BESS will contribute to meeting both of these, as well as helping lower overall cost of energy that consumers pay, NamPower managing director Kahenge S Haulofu said. 

“As one of the first utility-scale storage projects in Southern Africa, the Namibia battery storage project BESS can be described as a flagship project,” Barbara Pirich, KfW’s country director for Namibia said at a signing ceremony held earlier this month.

“As the project is the first of its kind in Southern Africa, it fulfils a pioneering function – it is expected that subsequent projects in the same field will benefit substantially from the experience gained from his project.”

Read Next

July 30, 2025
Utility and power generation firm EnBW has presented a 400MW/800MW BESS project proposal to a municipal council in Germany, for deployment at its Philippsburg nuclear power plant which is in the process of being decommissioned.
July 30, 2025
Perhaps best known outside the US for peaches and its emergence as a rival to Hollywood, Georgia is also thirsty for electric capacity and has become a hub for battery manufacturing, writes Allan Oduor of Enertis Applus+.
July 30, 2025
Maharashtra State Electricity Distribution Co (MSEDCL) has launched a multi-gigawatt battery storage tender supported by Viability Gap Funding (VGF).
July 29, 2025
The government of Portugal has announced plans to invest €400 million (US$466 million) to improve its grid management capabilities and increase its battery energy storage system (BESS) capacity.
July 22, 2025
The power generation arm of Manila Electric Company (Meralco) is developing its second large-scale battery storage project.

Most Popular

Email Newsletter