Premium

Dominion receives approval to develop 400MWh BESS in Virginia after fire safety concerns alleviated 

September 19, 2025
LinkedIn
Twitter
Reddit
Facebook
Email

Regulated utility Dominion Energy last week received the green light from local officials to develop a 100MW/400MWh BESS in Fauquier County, Virginia. 

Fauquier County’s Board of Supervisors (BoS) approved a special exception for the project at its most recent September meeting, after previously postponing its final decision due to concerns expressed surrounding fire safety.  

The area that will host the utility-owned battery energy storage system (BESS) has been targeted by developers in recent times, with several proposals for adjacent data centers currently under consideration.  

Remington BESS, nestled in data center alley 

The so-called Remington BESS facility will comprise 174 individual storage enclosures located on the outskirts of Remington encompassing approximately 72 acres of land, adjacent to a solar facility and fossil gas that are both owned by Dominion. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The project will form part of PJM Interconnection’s electricity grid, with connection achieved via pre-existing 230kV infrastructure present on the site. Under the terms of the special exception, Dominion has two years to deliver on the project. 

Also proposed near Dominion’s Remington BESS are four huge data center campuses. Although only one of these has so far been approved by local officials, Northern Virginia is home to one of the world’s largest densities of data centers, with some referring to this area as “data center alley.” 

Although Dominion is proposing to develop several clean energy projects to serve this growing demand from data centers, it’s also proposing to continue burning fossil fuels well into the next decade.  

As outlined within its most recent resource plan, Dominion plans to continue operating its fossil fuel fleet until 2039 in order to meet expected demand. The utility has also not addressed how it intends to become emissions free by 2045, as required under Virginia State Law.  

Alongside extending the life of its current fossil fuel plants, Dominion is seeking approval from the State Corporation Commission (SCC) to build a new 1,000MW fossil gas plant in Chesterfield County, Virginia.  

The regulatory case is only in its early stages, however, the plans have already drawn widespread criticism from all corners of society due to the project’s highly polluting nature. 

Collaboration with local officials 

Despite the County’s Planning Commission recommending approval of the project, the BoS deferred Dominion’s application during its August meeting in order to further evaluate the risks surrounding potential BESS fires. 

After the August meeting, several local officials and representatives from the local fire department met with Dominion staff at the utility’s operational 20MW/80MWh Dry Bridge Energy Storage located in Midlothian, Virginia. 

Early development of the Dry Bridge project, which happens to be Dominion’s largest operational BESS, was completed by East Point Energy who sold the project as part of a utility-administered RFP. 

As stipulated within the special exception for Remington BESS, Dominion is required to operate the facility in accordance with several internationally recognised codes and standards. 

This includes those created by the National Fire Protection Association (NFPA), who this week released its hotly-anticipated 2026 edition of its 855 Standard for the Installation of Stationary Energy Storage Systems. 

Additionally, each battery container at the Remington site will be spaced at least 25-feet apart, which exceeds the requirements of NFPA 855. Dominion will also reimburse any expenses incurred by local fire personnel in the event of a fire at the site. 

During the recent BoS meeting, Senior County Planner Kara Marshall said they “received extensive knowledge about how all of these fire safety protocols are put in place” during the site visit. 

Unusually, no one was present to speak during the public hearing portion of the meeting, which was swiftly followed by the BoS’ unanimous approval of the project. 

Read Next

Premium
November 19, 2025
An energy storage agreement (ESA) between Toronto, Ontario-headquartered developer Hydrostor and California community choice aggregator (CCA) Central Coast Community Energy (3CE) is set to be amended for the third time. 
November 18, 2025
US residential solar and energy storage installer Sunrun has posted revenue of US$724.6 million in the third quarter of this year, as the company implements its “storage-first strategy”.
Premium
November 14, 2025
The US development arm of Milan, Italy-headquartered developer Nadara has encountered a setback in its pursuit of a 200MW hybrid BESS destined for Arizona.
Premium
October 31, 2025
Two investor-owned utilities (IOUs) are seeking regulatory approval to acquire an under-development solar and storage project located in Waushara County, Wisconsin. 
October 24, 2025
Redwood Materials has closed a US$350 million Series E funding round to scale up its critical battery materials and energy storage businesses.