Dominion Energy announces energy storage pilot projects in Virginia

By Conor Ryan
LinkedIn
Twitter
Reddit
Facebook
Email
These four utility-scale battery storage pilot projects have a combined installation capacity of 16MW and are the largest projects of their kind in Virginia. Image: Flickr / Sabreguy29

Dominion Energy Virginia has signed off on four battery storage pilot projects to help open avenues for additional energy storage technology needed to support the company's boost in renewables and to improve grid reliability.

These four utility-scale battery storage pilot projects have a combined installation capacity of 16MW and are the largest projects of their kind in Virginia. The installations were filed with the State Corporation Commission (SCC) for approval Friday and are enabled by the Grid Transformation & Security Act of 2018, which lets Dominion Energy invest in up to 30MW of battery storage pilot projects.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Mark D. Mitchell, vice president – generation construction, said: “Energy storage is critical to providing continued reliability for our customers as we expand our renewable portfolio. Battery storage has made significant strides in recent years, in both efficiency and cost. These pilot projects will enable Dominion Energy to better understand how best to deploy batteries to help overcome the inherent fluctuation of wind and solar generation sources.”

Joe Woomer, vice president – grid & technical solutions, added: “These pilot projects will allow us to analyze the use of energy storage for grid stability support as an alternative to traditional upgrades of grid equipment, such as transformers. Battery storage has the potential to serve a key role in maintaining reliable service for our customers as we work to integrate renewables and improve grid resiliency.”

The four proposed Central Virginia-based lithium-ion projects will cost approximately US$33 million to construct and are expected to be operational by December 2020. The pilots would then be evaluated over a five-year period. 

Two battery systems totalling 12MW will be located at the Scott Solar facility in Powhatan County, while a 2MW installation will be built at a substation in Ashland. Another 2MW battery will be installed at a substation in New Kent County, and will serve a nearby 20MW PV project. 

Read Next

July 25, 2025
Estuary Power has commenced operations of the 185MW solar, 400MWh battery energy storage system (BESS) Escape project in Lincoln County, Nevada, US.
July 24, 2025
CEA has recently released two battery energy storage system (BESS) reports for Q2 2025, the Energy Storage System Price Forecasting Report and the ESS Supply, Technology, and Policy Report.
July 23, 2025
Optimiser GridBeyond, over the summer, began operating the 200MW/400MWh Big Rock Battery Energy Storage System (BESS) in El Centro, California, with Gore Street Energy Storage Fund (GSF).
July 23, 2025
Three companies, Ultion Technologies, Ultium Cells and SK On have recently announced plans to begin manufacturing lithium iron phosphate (LFP) battery cells in the US.
July 23, 2025
The US Department of Commerce has provisionally decided to impose anti-dumping (AD) tariffs on active anode material (AAM) product imports from China of 93.5%, bringing the total tariff on them to 160%.

Most Popular

Email Newsletter