Consultation for 5.4GW renewable energy and battery project to power metals mining in Australia

LinkedIn
Twitter
Reddit
Facebook
Email
Fortescue Metals Group autonomous drilling rig in the Pilbara, Western Australia. Image: Fortescue Metals Group.

A public consultation period has opened on plans for a vast renewable energy project including large-scale battery storage which would be used to power mining operations for Australian metals company Fortescue. 

Fortescue Metals Group has submitted its Uaroo Renewable Energy Hub proposal to the Environmental Protection Authority of Western Australia, with the public consultation period now open for a week until 15 February.   

According to documents hosted on the Authority’s site, the project, in the mineral rich Pilbara region of Western Australia, would consist of up to 340 wind turbines and a solar farm, which between them would have a maximum energy generating capacity of 5.4GW. 

Repurposing land used mostly for cattle grazing, the site proposal also includes substations and other infrastructure and hosting up to 9,100MWh of battery storage, which would comfortably make it the largest battery project in the world. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The world’s largest battery storage project to date is the 1,600MWh Moss Landing Energy Storage Facility in California, although recent plans were announced to take that up to 3GWh.  

The Pilbara Uaroo Renewable Energy Hub would take up to seven years to construct and have a maximum project life of 42 years, although infrastructure would be maintained and then replaced approximately every 30 years as assets reached their end of life. 

The application has been made by Fortescue’s subsidiary Fortescue Future Industries (FFI) and its energy asset arm Pilbara Energy. FFI aims to drive the group’s transformation into a powerhouse of the energy transition economy, with its other activities including a heavy emphasis on promoting green hydrogen, of which Fortescue founder and chairman Dr Andrew Forrest is an enthusiastic supporter. 

Mining operations, which are often remote and not connected to national or regional grid infrastructure, can benefit both economically and environmentally from onsite or nearby renewable generation backed with energy storage, due to their otherwise being dependent on expensively transported fossil fuels and their attendant, maintenance-heavy generation equipment.

Numerous recent projects have been reported on from this sector, including the recent completion of BHP’s first off-grid renewables projects, with solar PV and battery storage, also in Western Australia. The vast majority however, pertain to reducing site emissions and increasing penetration of renewables, rather than completely powering operations with solar and wind, as appears to be the case with the latest Fortescue project proposal.

Read Next

October 15, 2025
Publicly-owned energy company CleanCo Queensland’s 250MW/500MWh Swanbank battery energy storage system (BESS) has officially registered with AEMO and commenced its testing and commissioning phase.
October 14, 2025
Spanish IPP Grenergy has begun construction on a 340MW solar project with 960MWh of energy storage in El Cabrero, located in Chile’s Biobío region. 
October 14, 2025
Developer Epic Energy has commenced commercial operations at its 100MW/200MWh Mannum battery energy storage system (BESS) in South Australia.
Premium
October 14, 2025
Battery storage equipped with optimisation platforms not specifically designed for Australia’s NEM missed revenue opportunities during the 10 October price spike, according to Sahand Karimi, co-founder and CEO of OptiGrid.
Premium
October 13, 2025
A total of 49.4GW/136.5GWh of grid-scale BESS came online in the first nine months of the year, up 36% compared to the same period in 2024.