Connecticut utilities Eversource, United Illuminating (UI) and a quasi-state bank have together launched the next 100MW tranche of a programme aimed at incentivising 580MW of customer-sited energy storage projects.

Connecticut Green Bank announced the launch of the Energy Storage Solutions Commercial Tranche 2 two years ahead of schedule due to demand yesterday (15 March). The first 50MW of the programme was launched in January 2022, reported by Energy-Storage.news at the time.

The programme provides upfront and performance-based incentives for the installation of battery storage on commercial and industrial (C&I) and residential sites. As well as improving resiliency and reducing bills for the customers, the battery systems pay out for 10 years as the systems send energy to the grid when it’s most needed.

The first tranche has seen 27 C&I projects from six developers approved totalling 46.4MW/139.4MWh of energy storage – 3-hour duration – and another 1MW of residential systems. It is being overseen by Connecticut’s Public Utilities Regulatory Authority (PURA).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Working with our utility colleagues as co-administrators of Energy Storage Solutions, we look forward to the interconnection and dispatch of these systems around our state,” says Sergio Carrillo, Managing Director of Incentive Programs for the Connecticut Green Bank, which will be administering the programme alongside Eversource and UI.

“We are seeing more and more small businesses and critical community facilities installing battery storage through the program,” he added.

The financial incentives are spelt out in the table below from the Energy Storage Solutions website.

The site also says that deployments must use six pre-approved ESS solutions. The six for C&I projects are specific models from Cadenza, Caterpillar Inc, ELM Fieldsight, Milton CAT, Socomec and Tesla, its Megapack 2. Eligible residential solutions are from Enphase Energy, Generac PWRcell and Sunpower.

The New England state committed to a 1,000MW energy storage deployment target for 2030 back in 2021, which includes projects deployed through this programme.

Energy-Storage.news’ publisher Solar Media will host the 5th Energy Storage Summit USA, 28-29 March 2023 in Austin, Texas. Featuring a packed programme of panels, presentations and fireside chats from industry leaders focusing on accelerating the market for energy storage across the country. For more information, go to the website.

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

March 4, 2026
Utility-scale battery storage developer Jupiter Power’s 700MW/2,800MWh Trimount battery energy storage system (BESS) in Everett, Massachusetts, US, has been approved by state officials.
March 3, 2026
3.6GWh of solar-plus-storage developments have progressed in Australia this week, with Edify Energy partnering with DT Infrastructure and Flow Power acquiring a 60MW project.
March 3, 2026
Oregon-based utility company Portland General Electric has finalised agreements for more than 1,000MW of new renewable energy and BESS projects.
March 3, 2026
The Governing Board of the Puerto Rico Electric Power Authority (PREPA) has approved renewables developer Polaris Renewable Energy’s battery energy storage system (BESS) standard offer (SO1) agreement.
March 2, 2026
Zinc hybrid cathode battery and storage system maker Eos Energy reasserted its vision for 2026 and beyond in its Q4 and full-year 2025 financial results.