Community energy utilities in California investigate long duration energy storage

By Andy Colthorpe
LinkedIn
Twitter
Reddit
Facebook
Email
First Solar Series 6 thin-film solar panels: the Ohio-headquartered company recently signed a solar-plus-storage PPA with two of the participating Community Choice Aggregator groups in California. Image: Andy Colthorpe / Solar Media.

A group of 11 community-focused energy utility groups in California have issued a Request for Information on long duration energy storage technologies that could be connected to the California Independent System Operator (CAISO) grid.

Community Choice Aggregators (CCAs) are permitted to supply energy to residents in several US states. In California CCAs operate in the service areas of the major investor-owned utilities and benefit from the IOUs infrastructure, while being able to freely determine their energy suppliers and generation mix. Deanne Barrow, a senior associate at law firm Norton Rose Fulbright, who has worked on several deals involving CCAs, told Energy-Storage.news recently that the CCAs role in procuring energy in the US is growing.

Energy-Storage.news has reported on several moves by CCAs to procure energy storage, both standalone and in combination with solar PV. Most recently, in early April this year, CCA CalChoice picked esVolta for a 15MW / 60MWh lithium-ion battery storage system to help provide Resource Adequacy in Santa Paula, a city in California’s Ventura County.

Later that month, thin-film solar technology company and project developer First Solar signed power purchase agreements (PPAs) with CCAs Monterey Bay Community Power (MBCP) and Silicon Valley Clean Energy (SVCE) for a 100MW solar PV plant combined with 20MW / 50MWh of battery energy storage systems.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Last week, the long duration request for information was published jointly by MBCP, SVCE and nine other CCAs: Clean Power Alliance of Southern California, CleanPowerSF, East Bay Community Energy, Marin Clean Energy, Peninsula Clean Energy, Redwood Coast Energy Authority, San Jose Clean Energy, Sonoma Clean Power and Valley Clean Energy.

The groups are collecting information to help with their long-term resource planning, through which a need for long duration storage has been identified. The ‘Joint CCAs’ group also said the information may inform a “subsequent long-duration storage request for offers” that might be issued “as soon as this summer”, either by the CCAs in some combination, or individually.

Respondents should meet the requirement to provide long duration energy storage that is able to discharge at full capacity for eight hours minimum, is able to interconnect directly to transmission or distribution networks and can participate in CAISO electricity markets. Resources must also meet minimum requirements for Resource Adequacy as stipulated by CAISO and the regulator, the California Public Utilities Commission. The Joint CCAs also want to know the pricing for a 15-year contract in US$ per kW-month for “up to 250MW of eight-hour storage (up to 2,000MWh)”.

The request is technology agnostic and respondents could offer anything from different types of batteries to thermal, chemical and mechanical storage and anything else that meets the request’s requirements. The CCAs want technologies that could achieve commercial operation by the beginning of 2026 and have a preference for “technologies that have been successfully demonstrated at commercial scale and have existing supply chains,” as well as those that minimise or mitigate “non-energy” environmental impacts.

Respondents have until 1 July 2020 to send their information. Full details can be found here on the Marin Clean Energy website.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

Premium
September 17, 2026
Energy-Storage.news Premium speaks with Randolph Mann, CEO at developer esVolta at the 2026 US Battery Asset Management Summit in Garden Grove, California.
Premium
September 16, 2026
Energy-Storage.news Premium speaks with David Miller, CCO of optimiser Gridmatic, at the 2026 US Battery Asset Management Summit in Garden Grove, California.
September 16, 2026
Interconnection costs for utility-scale energy storage in California are significantly lower than in other major US markets, with developers also benefiting from network upgrade cost reimbursements unavailable elsewhere, according to a senior executive at Rev Renewables.
September 16, 2026
OCP Green Energy has completed the installation of a 25MW/125MWh battery energy storage system (BESS) in Benguerir, Morocco.
September 16, 2026
Recent moves from the US federal government could prove more damaging to US renewable energy deployment than foreign entity of concern (FEOC) compliance requirements, according to legal and industry experts.