BESS trial starts in EU-supported Slovenia-Croatia grid synchronisation programme

April 14, 2022
LinkedIn
Twitter
Reddit
Facebook
Email

A 10MW/50MWh battery energy storage system (BESS) spread across two substations in Slovenia has started a trial and testing period.

The BESS projects are located at the Okroglo and Pektre substations and started their trial period this month, the company launching them announced. They are part of the SINCRO.GRID project, a smart grid investment project in Slovenia and Croatia which was launched in 2016 and with €40 million (US$43.25 million) in financing from the European Union.

It aims to increase grid flexibility in both countries. Specifically, the project aims to improve the voltage quality and frequency control, as well as increase the capacity and flexibility of the network for a more reliable supply. It also aims to help integrate increased amounts of renewable energy sources (RES) onto the grid.

The partners in the project are the Slovenian and Croatian transmission operators ELES and HOPs, respectively, and the two countries’ distribution system operators, SODO and HEP ODS. The SINCO.GRID project was born out of the realisation that the two countries faced similar technical challenges.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

It will be managed by the transmission operators, each of whom will be responsible for the implementation of technologies in their respective system, while distribution system operators providing information about the operation of Renewable Energy Sources (RES) on the grid. This will help the transmission operators to forecast ancillary service needs.

The project website adds that the control centres of the distribution and transmission operators will be connected via ICT infrastructure and system integration primarily using the semantic model (Common Information Model or CIM).

Other aspects of the SINCRO.GRID project include a virtual cross-border control centre (VCBCC) and a dynamic thermal rating (DTR) to assess operating limits and better utilise transmission lines and transformers. The VCBCC links the electricity systems of the two countries and will integrate the DTR, new compensation devices for reactive power control and the BESS projects. Shunt reactors have been installed at substations in Mraclin and Melina, in Croatia.

Most energy storage news in Slovenia has come from private company NGEN which has launched two BESS projects using Tesla’s Megapack product.

Read Next

April 16, 2026
Neoen Australia has referred its 3,200MWh Bondo wind-plus-storage project for federal environmental assessment.
Premium
April 13, 2026
Envision’s Behzad Naderi believes that Australia’s hybridisation rules are reshaping development and connection processes across the NEM.
April 13, 2026
A 150MWh system has been granted approval in Australia, whilst a 1,000MWh system has been submitted for federal consideration.
April 10, 2026
New South Wales has been warned that it must accelerate the development of battery energy storage systems to meet its 2030 targets.
Premium
March 31, 2026
Climate Energy Finance’s Tim Buckley argues that geopolitical instability exposes Australia’s oil dependency and positions the country as a safe haven for international renewable energy capital.