Battery storage could meet Illinois resource adequacy need as fossil fuels retire, analysis finds

LinkedIn
Twitter
Reddit
Facebook
Email

Illinois can address its resource adequacy shortfall by replacing the US state’s retiring fossil fuel plants with 2,972MW of energy storage, and without significant transmission upgrades.

That’s according to a recent study prepared for the US environmental advocacy group Natural Resources Defence Council (NRDC) by Alabama-based advisory firm Astrape Consulting, in response to a 2022 report issued by PJM Interconnection which raised concerns surrounding grid reliability following the passing of Illinois’s landmark Climate and Equitable Jobs Act (CEJA) in 2021.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

US$2 billion in regional transmission upgrades

The legislation requires the retirement of all Illinois coal-fired power plants, with the exception of Dallman Unit 4 and Prairie State Generating Station, by 2030 and all methane (natural) gas-fired plants to be retired or switched to burning green hydrogen by 2045.

The 2022 PJM report found that Illinois’s fossil-fuel phase-out would result in the state needing to import a “substantial amount of remote replacement power” to address the estimated loss in dispatchable power between 2030-2045 across Illinois in both PJM and MISO regions.

Calculations from PJM estimated the increase in electricity imports to cost an approximate US$700 million in transmission upgrades by 2030 and an additional US$1.3 billion by 2045.

Potential for extended fossil fuel plant operation

Despite PJM acknowledging that “new generation resources at the same points where units are retiring, or in similarly favourable locations, could decrease the transmission cost estimates,” it did not evaluate the impact of new energy storage resources within Illinois.

Conversely, PJM concluded it might “need to request that certain units operate beyond their desired deactivation dates”, referring to the continued operation of the state’s polluting fossil fuel plants, which the legislation was brought in to stop.

The recent NRDC report built on the 2022 PJM study by performing a resource adequacy assessment on the addition of BESS facilities at fossil-fuel plants set to be retired by 2030 in MISO Zone 4 and PJM’s ComEd service territory – referred to as the “Illinois Zone”.

In order to determine whether reusing interconnection capabilities of retired fossil-fuel plants would be a feasible strategy, the analysis carried out in the NRDC report limited new storage capacity to not exceed that of the retiring plants.

Resource adequacy simulation for four scenarios

The recent report prepared for the NRDC simulated four resource adequacy scenarios for the Illinois Zone, with each of the cases building on the previous one. This was measured against an industry standard 0.1 loss of load expectation (LOLE) target – equating to electricity demand outstripping supply no more than one day across a 10-year period.

The four cases were as follows:

  1. Base case: existing installed capacity in Illinois (as of March 2024).
  2. Post-CEJA: Base Case minus fossil-fuel retirement capacity as mandated by CEJA by 2030 (estimated 11,588MW reduction).
  3. CEJA plus queue: post-CEJA case plus expected additions from the Generator Interconnection Queue (GIQ) (estimated 7,727MW addition).
  4. CEJA plus storage – CEJA plus queue plus required storage to meet LOLE target.

3GW of BESS to address shortfall

The analysis (displayed in the following graph below) found that although the Base Case exhibited a 4,971MW surplus, both Post-CEJA and CEJA plus queue scenarios presented shortfalls, at 5,065MW and 2,213MW, respectively.

In order to meet the 0.1 LOLE target in the CEJA plus storage scenario, the report concluded that 2,972MW worth of 4-hour duration batteries would be needed.

A graph displaying the results of the four scenarios prepared by Astrape Consulting for the NRDC. Source: Illinois Deactivations – Maintaining Reliability with Energy Storage report (page 4).

Astrape Consulting carried out a separate sensitivity study to determine the required capacity of 8-hour durations batteries to meet the LOLE target.

It concluded that a lower 2,243MW worth of batteries would be required, drawing attention to the importance of longer-duration storage systems, which the California Energy Commission (CEC) also highlighted in a recent study covered by Energy-Storage.news Premium.

Difference in study assumptions and metrics

Although the PJM and NRDC reports both utilised the same methodology for estimating GIQ additions, there was a very large discrepancy between the two figures – with the PJM report estimating 1,723MW of additional GIQ capacity, and the more recent report for the NRDC estimating a much larger 5,605MW.

Astrape Consulting addressed this difference within its recent report citing the use of more updated GIQ data. However, this discrepancy is still worth pointing out.

The NRDC report didn’t quantify the costs associated with the deployment of 3GW worth of BESS, which would likely be substantial, although it stated that this “could be an area of future development”.

It’s also worth noting that, unlike the PM study which looked all the way until 2045, the analysis carried out by Astrape Consulting only took place until 2030.

The full report with all of its findings can be found here.

Illinois ‘Coal to Solar Energy Storage’ grant programme

The Illinois Department of Commerce & Economic Opportunity has created several programmes since instating CEJA to assist in decarbonising its grid, including the “Coal to Solar Energy Storage” initiative which saw funding be issued to the developers of five energy storage projects located at the site of closing or soon to be closed coal-fired plants.

Fortune 500 company Vistra Energy was the recipient of three of these grants in 2022 that will see the developer receive US$40.7 million for each project over a ten-year period, covered in Energy-Storage.News.

The three projects, located at the site of the developer’s Edwards, Havana and Joppa generation stations, will each provide the MISO region within Illinois with 37MW of storage capacity, scheduled to come online next year.

12 November 2024
San Diego, USA
As we see more storage projects become operational, the big question is “how to maximize your assets?” This event will prepare the industry for the road ahead, looking at the core fundamentals of asset management, understanding operational challenges, along with the latest optimization and software development. You can expect to meet and network with all the key industry players from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

Premium
September 5, 2024
Georgia Power has secured a battery and equipment supply agreement (BESA) with Tesla for a 500MW/2,000MWh BESS portfolio made up of four projects of varying sizes under development by the investor-owned utility (IOU).
September 5, 2024
The Q3 2024 edition of our downstream solar PV and energy storage journal, PV Tech Power, is now available to download.
Premium
September 4, 2024
Augmentation and end-of-life disposal look set to grow in significance in the next few years in the US, with nearly 1.5GW/3GWh of BESS projects now four years old or more.
Premium
September 3, 2024
The North American arm of Sweden’s Eolus Vind has secured financing and advanced the sales process for its 100MW/400MWh Pome standalone BESS facility located in San Diego County, California.
August 30, 2024
IPP Invenergy has put a 50MW BESS into commercial operations in Arizona, US, its 10th in the state.

Most Popular

Email Newsletter