Amazon buys ready-to-build Oregon solar-plus-storage project from bankrupt developer Pine Gate

January 21, 2026
LinkedIn
Twitter
Reddit
Facebook
Email

Global tech giant Amazon has been approved as the buyer of the 1.2GW Sunstone solar project in Oregon, one of the largest solar PV projects in the US.

The Sunstone site was developed and previously owned by Pine Gate Renewables, the US independent power producer (IPP), which filed for bankruptcy in November 2025. It includes 1.2GW of solar PV and 1.2GW of battery energy storage system (BESS) capacity, which is ready to build, having received permitting and approvals from the Oregon Energy Facility Siting Council (EFSC).

Amazon’s acquisition was approved by the Bankruptcy Court for the Southern District of Texas, which granted its offer of US$83 million in cash via its specific project subsidiary, Oregon Solar I.

The move follows Amazon’s complaints back in November that an Oregon utility was not supplying sufficient power to its data centre projects in the state, where it has built numerous cloud computing data centres close to the banks of the Columbia River. Once fully operational, the Sunstone solar-plus-storage project will be one of the most significant renewable energy generation projects in the US.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Since declaring bankruptcy, Pine Gate’s roughly 10GW of project assets have been offered to the market, though the company says it has sufficient liquidity to continue operating in the meantime. 

To read the full version of this story, visit PV Tech.

Read Next

March 31, 2026
The Michigan Public Service Commission has approved six battery energy storage system (BESS) projects totalling 1,332MW of capacity in the US state.
March 31, 2026
BESS safety issues become all too visible when it’s already too late, but a considered approach through the full lifecycle can mitigate these and many other risks, writes Sunny Rai from Intertek.
March 30, 2026
Chile continues to be Latin America’s hotspot for energy storage deployments, with a major new deal for Grenergy and Engie bringing a project online in the past week.
March 27, 2026
Form Energy has signed a 12GWh supply agreement in the US for its iron-air batteries with AI data centre infrastructure developer Crusoe.
March 27, 2026
IPP Akuo will soon start building a 2.75-hour BESS project in Borba, Portugal, integrated into its 181MW Santas solar PV plant.