ACE Power submits EPBC application for 3.6GWh BESS in Queensland, Australia

LinkedIn
Twitter
Reddit
Facebook
Email

Renewable energy developer ACE Power has submitted its 3.6GWh 4-hour duration Nebo battery energy storage system (BESS) in Queensland to the Australian government seeking approval under its Environment Protection and Biodiversity Conservation (EPBC) Act.

The 900MW BESS project, which will cover 97 hectares, will also include an extension to Powerlink’s Nebo substation. Two underground 275kV circuits will connect the project to this substation.

The project will be located near the rural town of Nebo in the Isaac region, around 956km north of the state capital, Brisbane. It will import electricity from the grid, which will then be stored and exported during peak demand.

According to documents submitted to the EPBC Act, the project will have two 450MW stages that could be developed separately or concurrently. Although the specific details of the BESS technology were not disclosed, the company confirmed that it will utilise lithium-ion technology.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The project’s first stage will include developing 450MW of BESS, a switchyard, and transmission infrastructure alongside the access driveway to the project site. Stage two will add 450MW of BESS and a second switchyard.

ACE Power confirmed that the construction phase of the Nebo BESS will take 12 to 18 months and is likely to start in the first quarter of 2026, subject to timely planning approval.

Once operational, the project will operate for around 45 years, with a repowering scheduled after the first 20 years. ACE Power secured the rights to the land in the first quarter of 2023.

Another key aspect of the Nebo BESS is establishing a community fund to support the local population. Indeed, the project documents outline that the Nebo BESS community benefit fund is still being developed and refined, and a figure has not been touted at the time of reporting.

ACE Power’s Australian energy storage portfolio

ACE Power is developing several renewable energy projects in New South Wales, Queensland, Victoria, South Australia, and Western Australia, including BESS.

Perhaps the most notable of its projects is the Hillview Energy Hub Project, which is set to feature around 300MW of solar PV and 300MW wind generation in New South Wales. The project will also feature the company’s largest BESS in its portfolio, a 1,000MW/4,000MWh 4-hour duration system. This is dependent on site constraints and market conditions.

It is also worth noting that the project will be situated in the New England Renewable Energy Zone (REZ), aiming to deliver up to 8GW of new transmission capacity to help deliver further renewable energy generation to the grid.

Another large-scale 4-hour duration BESS the company in New South Wales is pursuing is the Talbingo Battery, a 450MW/1,800MWh system located 2.8km south of the town of Talbingo. The project is still in the early stages and will be submitted to the New South Wales Department of Planning, Housing and Infrastructure as part of a State Significant Development Approval application. Construction on the BESS is expected to commence in 2027.

The last notable development is proposed near the town of Claire in regional Queensland. A 140MW solar plus-storage site featuring a 500MW/2,000MWh BESS is being explored.

ACE Power received development approval in October 2017 for a solar PV power plant and BESS on the land. However, the developer is preparing to change the application to include a staged construction plan for both the BESS and the solar PV plant and a proposal for a larger BESS. This application was targeted for submission in the third quarter of 2024.

Energy storage in the EPBC Act

The EPBC queue, administered by the Federal government, aims to protect nationally threatened species and ecological communities. The approval must be received before a project can be developed. 

One of these large-scale projects submitted to the EPBC Act includes renewable energy infrastructure developer BE Power Group’s 800MW/9.6GWh Big-G pumped hydro energy storage (PHES) project in Queensland, Australia.

Another project recently submitted to the EPBC Act is Quinbrook Infrastructure Partners’ plans for a 750MW BESS co-located with a proposed polysilicon plant in Townsville, Queensland.

Squadron Energy, a renewable energy developer owned by one of Australia’s wealthiest citizens, Andrew Forrest, entered the EPBC Act to secure consent for an 8-hour duration 1,200MWh BESS in New South Wales, to be co-located with a 300MW wind project.

Similarly, the Australian entity of global renewable energy investor Cubico Sustainable Investments (Cubico) recently submitted two wind-plus-storage projects, both of which include a 200MW BESS, for approval under the EPBC Act.

8 September 2026
Barcelona, Spain
Battery & Energy Storage Tech Europe (BESTE) is Europe’s industrial scaling platform for stationary and industrial battery applications — not EVs. Taking place 8–9 September 2026 at Fira de Barcelona, BESTE brings together utilities, IPPs, energy-intensive industries, data centres, ports, rail, maritime, defence and aerospace OEMs — all deploying or integrating battery storage at scale. Over 100 companies already confirmed — including EDP Renewables, Acciona, Endesa, Naturgy, Neoen, Galp, Basquevolt and Veolia — alongside 40+ expert speakers and international institutional support from BEPA, BVES, LDES and Volta Foundation. Where Europe’s battery & ES ecosystem turns projects into reality.
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
15 September 2026
Berlin, Germany
Launching September 2026 in Berlin, Energy Storage Summit Germany is a new standalone event dedicated to Germany’s energy storage market. Bringing together investors, developers, policymakers, TSOs, manufacturers and optimisation specialists, the Summit explores the regulatory shifts, revenue models, financing strategies and technology innovations shaping large-scale deployment. With Germany targeting 80% renewables by 2030, it offers a focused platform to connect with the decision-makers driving the Energiewende and the future of utility-scale storage.

Read Next

July 24, 2026
ESS Tech Inc is deploying sodium-ion BESS in the US with Juniper Energy, while CATL deploys its sodium-ion technology in Eastern Europe with Solarpro.
July 24, 2026
In this news roundup, Grenergy, MaxSolar and Saft, and Amarenco have made significant advancements on BESS projects in Spain, Germany, and France.
Premium
July 23, 2026
ESN Premium speaks with Bryen Alperin and Sophie Brkovic of Foss & Company about the tax equity investor’s entrance into microgrids.
July 23, 2026
The Clean Energy Investor Group (CEIG) has published a report calling on the Australian government to prioritise consistent and timely implementation of the reformed Environment Protection and Biodiversity Conservation (EPBC) Act.
July 22, 2026
Activity in Italy’s grid-scale market is accelerating, with Sonnedix and the Strioga Family Foundation acquiring projects totalling over 1GWh combined, while BNZ and RWE have ordered BESS from Sungrow and LONGi respectively totalling 540MWh.