Ameren Missouri files application for BESS co-located with natural gas facility

LinkedIn
Twitter
Reddit
Facebook
Email
Ameren gas and energy storage centre
A rendering of the Big Hollow Energy Centre. Image: Ameren Missouri

Utility company Ameren Missouri has filed an application with the Missouri public service commission (PSC) to construct a natural gas and battery storage facility in the state.

Ameren’s application involves construction an 800MW natural gas energy centre co-located with a 400MW battery energy storage system (BESS) in Jefferson County.

Called the Big Hollow Energy Centre, the project will also assist Ameren Missouri with its recently announced energy storage goals. It plans to have a total capacity of 1,000MW by 2030 and 1,800MW by 2042.

In 2023, the company aimed to procure 800MW of battery storage in the Midcontinent Independent System Operator (MISO) service area, which represented a US$650 million investment.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

At that time, Ameren Missouri’s integrated resource plan (IRP) indicated that although the utility plans to keep investing in natural gas, as shown by Big Hollow, it is also dedicated to phasing out coal use.

Ameren’s levelised cost of energy (LCOE) modelling also found that battery storage was cheaper than simple cycle gas turbines but not cheaper than baseload combined cycled gas power plants.

Solar and storage installations are expected to decline with the passage of the tax reconciliation bill, and natural gas is still quite popular.

It may be the case that a greater number of energy storage projects are co-located with natural gas generation, which is a better alternative to coal but still represents a slower buildout of renewable energy infrastructure.

Ameren says that the natural gas portion of the project will be designed to deliver energy on the coldest winter days, hottest summer afternoons and to back up the grid when renewable generation is unavailable. The assets will operate independently of one another.

The utility notes that this is a similar use case to its Castle Bluff Energy Centre, an 800MW simple cycle gas facility built at a former coal site.

Ameren already owns the land to be used at Big Hollow and can leverage existing infrastructure and access to transmission lines, the company said.

Additionally, Ameren notes that Big Hollow will provide “significant investment” and jobs to the local community, and with timely regulatory approval, the energy centre will be operational in 2028.

Ajay Arora, senior vice president and chief development officer at Ameren Missouri said of the project:

“It is crucial to have a balanced mix of generation technologies, and equally important to strategically locate them across the region. This approach maximises the energy output from these resources.”

11 November 2025
San Diego, USA
The 2024 Summit included innovative new features including a ‘Crash Course in Battery Asset Management’, Ask-Me-Anything formats and debate-style sessions. You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
24 February 2026
InterContinental London - The O2, London, UK
This isn’t just another summit – it’s our biggest and most exhilarating Summit yet! Picture this: immersive workshop spaces where ideas come to life, dedicated industry working groups igniting innovation, live podcasts sparking lively discussions, hard-hitting keynotes that will leave you inspired, and an abundance of networking opportunities that will take your connections to new heights!

Read Next

October 3, 2025
EDF Renewables has brought its 300MWh Milagro project online in New Mexico, while Enlight Renewable Energy has secured US$340 million in tax equity financing for its 940MWh Roadrunner project in Arizona.
October 3, 2025
More than 30 stakeholder organisations in the US energy storage value chain have formed a new association to represent common interests.
October 2, 2025
Major US utility company Duke Energy has filed its biennial long-range energy modernisation plan for North and South Carolina, US. The plan includes a 5,600MW battery storage target.
October 2, 2025
Solar PV and energy storage firm Canadian Solar has entered into battery storage agreements (BSAs) and long-term services agreements (LTSAs) with Aypa Power for the Elora and Hedley battery energy storage system (BESS) projects in Ontario, Canada.
October 2, 2025
Two battery energy storage systems (BESS) from Origin Energy and Eku Energy, totalling 2,200MWh, have been submitted to Australia’s EPBC Act.

Most Popular

Email Newsletter