400MWh state-owned Tesla BESS begins commercial operations in Queensland, Australia

LinkedIn
Twitter
Reddit
Facebook
Email

State-owned energy company CS Energy announced yesterday (25 July) that its 200MW/400MWh Greenbank battery energy storage system (BESS) has started commercial operations in Queensland, Australia.

The 2-hour duration BESS features 108 Tesla Megapack 2XL units and is located in the rural residential suburb of Greenbank, southeast of Brisbane, the state capital.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

It is connected to the National Electricity Market (NEM), which spans Australia’s southern and eastern coasts as well as Tasmania. It is situated adjacent to Powerlink Queensland’s Greenbank substation, which supplies electricity to Southeast Queensland, particularly the Gold Coast, Logan and South Brisbane areas.

Site work for the Greenbank Battery commenced in late 2023, with a peak construction workforce of 60 people. The project officially began commercial operations in June 2025.

The BESS becomes the second utility-scale battery storage system that CS Energy has brought online after its 100MW/200MWh Chinchilla battery in Queensland’s Western Downs Region last year.

Like the Greenbank Battery, Chinchilla features 80 Tesla Megapack 2XL units. The Megapack is based on Tesla’s integrated solution, which includes lithium-ion (Li-ion) batteries, power conversion system (PCS), thermal management and controls.

Tesla Megapack 2XL units are also being used at Stanwell’s, another state-owned energy company, 300MW/1,200MWh BESS at the Stanwell Power Station in central Queensland. The first of the Megapack units arrived last week, with 324 set to be delivered in total in the coming months.

CS Energy worked with Tesla, Consolidated Power Projects, and Powerlink Queensland to deliver the Greenbank Battery.

 CS Energy CEO Brian Gillespie said the Greenbank BESS had gone through a “rigorous” testing and commissioning process, reaffirming beliefs that Australia has some of the toughest grid codes in the world.

 “CS Energy also undertook a detailed operational readiness program, which included employee training, critical risk assessments, and safety and design reviews,” Gillespie added.

CS Energy confirmed that the Greenbank BESS required an investment of AU$300 million (US$197 million) to fully develop.

Our publisher, Solar Media, will host the Battery Asset Management Summit Australia 2025 on 26-27 August in Sydney. You can get 20% off your ticket using the code ESN20 at checkout.

11 November 2025
San Diego, USA
The 2024 Summit included innovative new features including a ‘Crash Course in Battery Asset Management’, Ask-Me-Anything formats and debate-style sessions. You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
24 February 2026
InterContinental London - The O2, London, UK
This isn’t just another summit – it’s our biggest and most exhilarating Summit yet! Picture this: immersive workshop spaces where ideas come to life, dedicated industry working groups igniting innovation, live podcasts sparking lively discussions, hard-hitting keynotes that will leave you inspired, and an abundance of networking opportunities that will take your connections to new heights!

Read Next

July 25, 2025
Estuary Power has commenced operations of the 185MW solar, 400MWh battery energy storage system (BESS) Escape project in Lincoln County, Nevada, US.
July 25, 2025
Australia-based battery energy storage system (BESS) developer, owner and operator Stor-Energy has announced plans to build a 1,449MWh 10-hour duration BESS.
July 24, 2025
Fluence will provide its Mosaic software for a 200MWh battery energy storage system (BESS) in Victoria, Australia.
July 24, 2025
On 21 July, standalone BESS and solar-plus-storage each achieved new generation records in Western Australia’s SWIS.
Premium
July 23, 2025
Developer Rhynland Energy has applied to Massachusetts’ energy regulator for approval of a 180MW/720MWh standalone BESS, to the dismay of local authorities in the Town of Oakham.

Most Popular

Email Newsletter