Work is underway on an energy storage project in South Australia that will use biogas to generate power to be stored in modules of molten silicon, from startup 1414 Degrees.

Co-funded by the South Australian state Renewable Technology Fund, and by the company, the GAS-TESS (thermal energy storage system) commercial pilot project is being installed at Glenelg Wastewater Treatment Plant.

The project came about in response to a 2017 request from state government-owned SA Water, which sought a biogas generation-inputted way of storing energy. Mobilisation of the GAS-TESS project has begun, 1414 Degrees said, with system components already on their way to the site.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

What it will do

Biogas is creating during the wastewater treatment process. This is used to generate energy that can be stored in the molten silicon and then returned as both heat and as electricity. While the electricity can be used on the grid or to power onsite operations, the heat outputted by the system goes back into the wastewater treatment facility’s digestors to continue creating biogas. It is thought to be a 10MWh system according to earlier reports.

The company, named after the temperature at which the silicon stores energy, has built its own 10MWh demonstration module and is planning to build a scalable and replicable 200MWh ‘supermodule’ at a renewable energy facility. In May, Energy-Storage.news reported that 1414 Degrees was planning an IPO at AU$50 million (US$35.87 million) as it touted the possible advantages of its technology. The company then listed on the ASX in September, raising around AU$27 million.

“Embracing innovative, world-leading technology and ways of thinking, is essential to reducing our electricity costs and maintaining low and stable pricing for our customers. As well as realising the benefits of increased energy self-sufficiency, we can support South Australian innovation and, hopefully, lead a global charge to reduce the costs and environmental impacts of energy-intensive wastewater treatment operations,” SA Water chief executive Roch Cheroux said of the project.

“We expect to commission the GAS-TESS in March 2019 and provide immediate returns for SA Water, while at the same time building a foundation for the wider application of the 1414 Degrees technology at similar sites across the globe,” 1414 Degrees executive chairman Dr Kevin Moriarty said.

Read Next

November 26, 2026
The first units of a BESS have arrived at European Energy’s operational Mokoan solar PV plant in northern Victoria, Australia.
Premium
November 25, 2026
Elias Saba of Eku Energy spoke to ESN Premium about how data centre demand for shared equipment is affecting BESS development.
November 24, 2026
APA Group has started construction on its 72MW solar PV plant and 52MW/104MWh BESS at Mount Isa in north-west Queensland, Australia.
November 23, 2026
BESS account for 5.3GW of the 8.4GW of new projects added to Australia’s NEM since December 2025, according to AEMO.
November 20, 2026
Another BESS Industry Buzz, looking at what people are discussing in the industry plus some of the most notable quotes from the RE+ trade show, which concluded yesterday.