A 100MW battery storage facility in Co. Offaly in Ireland has this week been energised, having been developed as part of a partnership between local developer Lumcloon Energy and South Korea’s Hanwha Group.

Writing on social media site LinkedIn, Irish network operator ESB Networks said it had enabled the connection and energisation of the project – situated in the Lumcloon townland – on behalf of Lumcloon Energy, describing it as a “great achievement for battery storage” in Ireland.

The project was first announced in 2018, with another 100MW project at Shannonbridge also unveiled. Together, the two battery energy storage systems (BESS) were set to involve a €150 million (£135 million) combined investment, creating 240 jobs during construction and 10 subsequent to the systems going into operation.

A Lumcloon Energy spokesperson told our sister site Solar Power Portal and Energy-Storage.news that the two companies are progressing the delivery of both projects and that Lumcloon is “pleased to announce the energisation of the Derrycarney 110kV substation where the Lumcloon BESS will deliver its fast response capability”.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“The BESS facilities will provide fast response system services to the national power system. System services are required to support the transition to low carbon energy sources such as wind and solar,” Lumcloon project development manager Jack Bracken told Energy-Storage.news.

Construction of the Lumcloon project began in 2019, with the design and build contractor being Duggan Brothers with Suir Engineering, Malachy Walsh and Partners. It is on track to become operational in Q1 2021, with Shannonbridge to follow soon after, the spokesperson added.

The energisation of Lumcloon follows Statkraft completing its 11MW Kerry battery storage project in Ireland in January 2020, the first completed utility-scale battery storage project in the country. It partnered technology provider Fluence for the project, which used battery modules produced by LG Chem.

The battery is one to have secured a contract with Irish transmission operator EirGrid through its DS3 flexibility market, providing reserves to the national electricity grid. Of the 110MW available in the DS3 auction, 60MW was snapped up by London Stock Exchange-listed investment fund Gore Street Energy Storage Fund. This was split across two 30MW projects in the country, with Gore Street having recently applied to expand its portfolio in Ireland to 180MW.

This story first appeared on Solar Power Portal.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.
3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

October 9, 2026
South Africa’s government has put battery storage and power-to-gas technologies at the heart of the national long-term electricity supply and demand strategy.
October 9, 2026
South Korea’s Ministry of Climate, Energy and Environment (MCEE) has unveiled its KRW1,000 trillion (US$747 billion) Korean Green Transformation (K-GX) industrial strategy.
October 7, 2026
Having just begun construction on a 2.8GWh BESS in Belgium, Giga Storage has progressed its 1.4GWh project in Germany to the ready-to-build stage.
October 6, 2026
Japanese trading company Sumitomo Corporation has invested in a utility-scale renewable energy park combining solar PV, wind and energy storage in India.
October 2, 2026
India’s Union Cabinet has approved US$ 19.3 billion Green Energy Corridor, including US$ 5.2 billion for 50GWh BESS through FY2032-33.