Younicos to design 49MW Centrica battery as technology ‘emerges from demonstrator’ projects

LinkedIn
Twitter
Reddit
Facebook
Email

Younicos’ experience in utility-scale storage projects in the UK extends to the 6MW Leighton Buzzard demonstrator (pictured) it participated in. Image: RES.
Battery storage specialist Younicos has been selected by Centrica to design the 49MW battery storage project that was last week awarded a 15-year Capacity Market contract.

The battery, to be built on the site of a former coal-fired power station in Roosecote, Cumbria, is to be owned and operated by Centrica, but the energy giant has selected Younicos to design the system, which is to be completed by winter 2018.

The sophisticated, lithium-ion based system will be capable of responding to fluctuations in energy demand in less than a second. It will be aided by software designed and developed by Younicos for batteries used in such applications.

Speaking to Energy Storage News, Younicos spokesman Philip Hiersemenzel said the system will be “one of the most sophisticated” batteries in the world when it is complete.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“It really underscores the versatility of what batteries can do and what they can do for the grid, for secure energy supplies and also for the people that operate them,” he said.

The Roosecote project is to use architecture developed off the back of Younicos’ participation in both Europe’s first commercial battery project in Schewin, Germany, and the software and controls it provided for UK Power Networks’ 6MW demonstrator project in Leighton Buzzard.

Hiersemenzel is, however, of the belief that the UK market is now emerging from the stage at which utility-scale batteries are considered demonstration projects, with the recent EFR and Capacity Market tender results providing ample evidence of confidence in the technology.

“I think the technology is really moving from being a demonstrator and into the market place. That’s become clear. We see the UK rapidly moving towards the commercialisation of batteries. It’s no longer a question as to whether they’re viable, it’s how to best deploy them,” he said.

At 49MW the battery stands to be the largest in the UK and among the largest in the world. This, Hiersemenzel said, would present its own challenges, but he is confident that Younicos has garnered the experience and requisite knowledge to see the project through, adding: “It reflects what we’ve learned over the years and what the market needs in terms of technical requirements and how best to handle the batteries.”

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.
13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

June 19, 2026
Developer BLT Energy has received development approval for the 800MW/4,800MWh Red Gully BESS in Western Australia.
June 19, 2026
Energy storage developer Eku Energy has submitted two BESS, each sized at 300MW and 1,200MWh, for assessment under Australia’s EPBC Act.
June 18, 2026
Energy storage developer-operator Aypa Power and utility Salt River Project (SRP) have brought the 250MW/1,000MWh Pediment energy storage project online in Mesa, Arizona.
June 18, 2026
Fire and Rescue NSW (FRNSW) in Australia has set out its requirements for lithium-ion battery storage rooms and diesel generator structures in data centres.
Premium
June 15, 2026
ESN Premium speaks with ASL on the latest FERM tender results in South Australia and why batteries excelled.