Younicos’ experience in utility-scale storage projects in the UK extends to the 6MW Leighton Buzzard demonstrator (pictured) it participated in. Image: RES.
Battery storage specialist Younicos has been selected by Centrica to design the 49MW battery storage project that was last week awarded a 15-year Capacity Market contract.

The battery, to be built on the site of a former coal-fired power station in Roosecote, Cumbria, is to be owned and operated by Centrica, but the energy giant has selected Younicos to design the system, which is to be completed by winter 2018.

The sophisticated, lithium-ion based system will be capable of responding to fluctuations in energy demand in less than a second. It will be aided by software designed and developed by Younicos for batteries used in such applications.

Speaking to Energy Storage News, Younicos spokesman Philip Hiersemenzel said the system will be “one of the most sophisticated” batteries in the world when it is complete.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“It really underscores the versatility of what batteries can do and what they can do for the grid, for secure energy supplies and also for the people that operate them,” he said.

The Roosecote project is to use architecture developed off the back of Younicos’ participation in both Europe’s first commercial battery project in Schewin, Germany, and the software and controls it provided for UK Power Networks’ 6MW demonstrator project in Leighton Buzzard.

Hiersemenzel is, however, of the belief that the UK market is now emerging from the stage at which utility-scale batteries are considered demonstration projects, with the recent EFR and Capacity Market tender results providing ample evidence of confidence in the technology.

“I think the technology is really moving from being a demonstrator and into the market place. That’s become clear. We see the UK rapidly moving towards the commercialisation of batteries. It’s no longer a question as to whether they’re viable, it’s how to best deploy them,” he said.

At 49MW the battery stands to be the largest in the UK and among the largest in the world. This, Hiersemenzel said, would present its own challenges, but he is confident that Younicos has garnered the experience and requisite knowledge to see the project through, adding: “It reflects what we’ve learned over the years and what the market needs in terms of technical requirements and how best to handle the batteries.”

Read Next

December 5, 2025
Developer BrightNight and independent power producer (IPP) Cordelio Power have announced financial close of the 200MW/800MWh Greenwater battery energy storage system (BESS) in Washington state, US.
December 4, 2025
PJM has awarded 23 battery energy storage system (BESS) resources, totalling 2.2GW, with interconnection agreements (IAs) in its first transition cycle (TC1) of the reformed interconnection process.
December 4, 2025
Zenith secures 25-year PPA with Northern Star for 532MW hybrid project featuring a 138MW/300MWh BESS at Kalgoorlie gold mine in Australia.
December 3, 2025
Stanwell bags rights to Quinbrook’s 6.24GWh Gladstone Energy Hub, combining 780MW battery energy storage with gas generation in Queensland.
December 2, 2025
The Puerto Rico Energy Bureau (PREB) has issued a resolution and order requiring the Puerto Rico Electric Power Authority (PREPA) to complete the Accelerated Battery Energy Storage Addition Programme (ASAP).