Younicos to design 49MW Centrica battery as technology ‘emerges from demonstrator’ projects

December 14, 2016
LinkedIn
Twitter
Reddit
Facebook
Email

Younicos’ experience in utility-scale storage projects in the UK extends to the 6MW Leighton Buzzard demonstrator (pictured) it participated in. Image: RES.
Battery storage specialist Younicos has been selected by Centrica to design the 49MW battery storage project that was last week awarded a 15-year Capacity Market contract.

The battery, to be built on the site of a former coal-fired power station in Roosecote, Cumbria, is to be owned and operated by Centrica, but the energy giant has selected Younicos to design the system, which is to be completed by winter 2018.

The sophisticated, lithium-ion based system will be capable of responding to fluctuations in energy demand in less than a second. It will be aided by software designed and developed by Younicos for batteries used in such applications.

Speaking to Energy Storage News, Younicos spokesman Philip Hiersemenzel said the system will be “one of the most sophisticated” batteries in the world when it is complete.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“It really underscores the versatility of what batteries can do and what they can do for the grid, for secure energy supplies and also for the people that operate them,” he said.

The Roosecote project is to use architecture developed off the back of Younicos’ participation in both Europe’s first commercial battery project in Schewin, Germany, and the software and controls it provided for UK Power Networks’ 6MW demonstrator project in Leighton Buzzard.

Hiersemenzel is, however, of the belief that the UK market is now emerging from the stage at which utility-scale batteries are considered demonstration projects, with the recent EFR and Capacity Market tender results providing ample evidence of confidence in the technology.

“I think the technology is really moving from being a demonstrator and into the market place. That’s become clear. We see the UK rapidly moving towards the commercialisation of batteries. It’s no longer a question as to whether they’re viable, it’s how to best deploy them,” he said.

At 49MW the battery stands to be the largest in the UK and among the largest in the world. This, Hiersemenzel said, would present its own challenges, but he is confident that Younicos has garnered the experience and requisite knowledge to see the project through, adding: “It reflects what we’ve learned over the years and what the market needs in terms of technical requirements and how best to handle the batteries.”

Read Next

December 17, 2025
According to the Q4 2025 US Energy Storage Monitor from Wood Mackenzie Power & Renewables and the American Clean Power Association (ACP), 2025 energy storage installations surpassed 2024 capacity.
December 17, 2025
It’s been a busy few weeks in the run-up to Christmas in Europe’s BESS project space, with M&A, final investment decisions (FID) and supplier deals in Germany, Belgium, Portugal, Italy, Finland, Romania and the UK totally around 800MW of capacity.
December 16, 2025
In this edition of the Energy-Storage.news US news roundup, EticaAG partners with Shell on battery immersion tech, Pacific Northwest National Laboratory begins utility-scale battery testing, and ON.Energy announces a transformer supply agreement.
December 16, 2025
 Utility Georgia Power has reached an agreement with the Public Interest Advocacy (PIA) staff of the Georgia Public Service Commission (PSC), that, if approved, will help lower energy costs and meet electricity demand in the state.
December 15, 2025
A new battery energy storage system (BESS) cybersecurity whitepaper from consultancy firm The Brattle Group and cybersecurity solutions provider Dragos claims that a single 100MW/400MWh BESS outage could result in US$1.2 million in monthly losses.