Virginia regulator approves utility Dominion’s 1GW solar, energy storage plan

By Jonathan Tourino Jacobo
March 23, 2022
LinkedIn
Twitter
Reddit
Facebook
Email

US utility company Dominion Energy Virginia has received approval from the Virginia State Corporation Commission (SCC) to expand its portfolio of solar and energy storage projects.

The expansion includes 15 new projects to be brought forward by Dominion Energy, as well as 24 power purchase agreement (PPAs) with third-parties for a total capacity of 1GW.

Ed Baine, president of Dominion Energy Virginia, said: “This is another significant milestone in Virginia’s transition to energy independence.

“These projects will support thousands of good jobs and hundreds of millions in economic activity in communities across Virginia. This is a positive step forward for our customers, the environment and Virginia’s economy.”

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The projects are expected to be completed between 2022 and 2023.

The company said the construction of the 15 projects is expected to generate US$880 million in economic benefits in the state as well as create more than 4,200 jobs.

The utility company had sent the proposal back in September 2021 to the SCC.

Clean energy policies enacted in Virginia in 2020 set a deployment target of 3.1GW of energy storage by 2035, the largest target of its type in the US until New York State doubled its previously-set 3GW target by 2030 to 6GW at the beginning of this year.

This story first appeared on PV Tech.

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

February 26, 2026
Energy storage developer and subsidiary of Canadian Solar, Recurrent Energy, has sold its 200MWh Fort Duncan battery energy storage system (BESS) project, located in Texas, US, to developer Hunt Energy Network.
February 26, 2026
The US Department of Energy (DOE) has closed a US$26.5 billion loan package to two wholly owned subsidiaries of utility Southern Company, in Georgia and Alabama, US.
February 26, 2026
Utility Xcel Energy will install 30GWh of US startup Form Energy’s iron-air batteries at a data centre in Pine Island, Minnesota, belonging to tech giant Google.
February 25, 2026
In this Energy-Storage.news roundup, FlexGen updates its EMS, LandGate launches a BESS site selection tool, ON.energy and Shoals target AI data centres, and Sunrun has a successful season of dispatching energy with PG&E.
Premium
February 25, 2026
In an interview with Energy-Storage.news Premium, Jay Jayasuriya, Principal at Sendero Consulting, argues that AI data centres are “convenient scapegoats” for grid failures