UK’s Gresham House says first-half 2024 results hit by ‘especially difficult market conditions’

By Kit Million Ross
October 2, 2024
LinkedIn
Twitter
Reddit
Facebook
Email

UK battery energy storage system (BESS) investment fund Gresham House Energy Storage Fund has announced its half-year results to the end of June 2024.

Operational capacity in MWh increased 46% year-over-year for the London Stock Exchange-listed fund, hitting 931MWh during the results period and crossing the 1GWh milestone shortly after the period ended. In MW, operational capacity rose to 790MW, up 34% from June 2023’s 590MW.

However, despite this capacity growth, operational portfolio revenues decreased 12.8% year on year, falling from £20.5 million (US$27.23 million) in June 2023 to £17.9 million. Earnings before interest, taxes, depreciation, and amortization (EBITDA) declined from £13.8 million to £10.4 million, with Gresham House blaming this 23.9% drop on “especially difficult market conditions” in the first quarter of this year. Net asset values also declined over H12024, dropping 19.91p to hit 109.16p per share.

Gresham House Energy Storage Fund has had something of a turbulent year, alongside other major players in the BESS sector. In a trading update in February this year, the company stated the UK BESS market was suffering from a “weak revenue environment”, a fact confirmed in April by the release of its audited annual results which showed the fund swinging to a £110 million loss from a £217 million profit the previous year. The fund made the decision to pause shareholder dividends, a choice also made by fellow investment fund Harmony Energy Income Trust.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

However, there may be good news on the horizon for Gresham House, as net revenues in July and August averaged at the highest levels of the year so far, roughly 25% higher than average net revenues in H12024.

Additionally, several major projects are set to go through energisation and commissioning in October and November this year, including the 40MW/80MWh Shilton Lane project, the 50MW/100MWh Elland project, and the augmentation of the Penwortham system, which will gain an additional 50MWh. The Melksham project in Wiltshire has begun its augmentation and is expected to begin operating with 150MWh in October before being expanded to 200MWh in December.

To read the full version of this story, visit Solar Power Portal.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

February 24, 2026
Panellists discussed M&A in large-scale BESS on the ‘M&A Market: How Attractive Is BESS Right Now?’ panel discussion at the Energy Storage Summit 2026.
February 24, 2026
How to enable bankability for large-scale BESS projects was the main topic of the opening panel discussion at the Energy Storage Summit 2026 which kicked off today (24 February).
February 20, 2026
A flurry of BESS project news from big-name players in Western Europe in the run-up to the Energy Storage Summit next week, with Neoen, Statkraft, Zenobē and Infranode moving projects forward in Germany, Ireland, the UK and Denmark. Highlights include a 15-year toll between Drax and Zenobē, and multiple 4-hour duration systems.
February 16, 2026
The UK just saw its biggest year of grid-scale battery storage deployments, but planning barriers “threaten to stall momentum,” according to one expert.
February 11, 2026
Netherlands-based iron-air long-duration energy storage (LDES) startup Ore Energy has completed a grid-connected pilot of its 100-hour iron-air LDES system at EDF Lab les Renardières in France.