UK: High BM skip rate for BESS bemoaned as H1 revenues crash

August 8, 2023
LinkedIn
Twitter
Reddit
Facebook
Email

Concern has been raised by the industry about battery storage consistently being overlooked in the UK Balancing Mechanism (BM), as the sector’s average revenues plummeted in the first half of 2023.

On behalf of its 80 members, trade body Electricity Storage Network (ESN) penned an open letter to transmission system operator National Grid expressing concerns over the Balancing Mechanism’s (BM) average ‘skip rate’ of 80% for large-scale batteries between November 2022 and May 2023.

The BM is used to balance supply and demand on each half-hour trading period of the day, and an asset is ‘skipped’ if a more expensive bid or offer is taken up instead of that asset. Market intelligence firm Modo Energy said the skip rate for batteries was even higher in 2023 alone, at 91%.

The ESN’s letter, penned at the end of July, said these actions cost UK consumers around £150 million (US$190 million). It blamed outdated IT systems and manual processes in National Grid’s Control Room resulting in batteries consistently being skipped over in favour of larger, carbon-intensive and more expensive assets like fossil fuel gas plants.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The ESN called for ‘greater urgency and a step-up in engagement between ESO and the storage sector’ and ‘more accurate data on the dispatch of storage vs other technologies, including making the Dispatch Transparency dataset, which states ESO’s reasons for skips, more transparent’.

It comes as the UK battery storage sector saw average revenues per MW plummet in the first six months of 2023 compared with the same period last year. Energy-Storage.news has been told this anecdotally by industry sources while Modo has published numbers on it.

The firm’s Revenue Benchmark for July was £5,892/MW (US$7,500/MW), up 54% from the previous month but down around two-thirds from a year prior. Across the first half of the year, Modo’s monthly benchmark was down a similar amount.

Energy-Storage.news reported on Modo’s analysis of ancillary service Firm Frequency Response (FFR) auction prices hitting a 3-year low in May, in the “surest sign yet that saturation is starting to bite”, Modo commercial data analyst Shaniyaa Holness-Mckenzie said at the time.

The topic of market saturation has come up a lot when discussing ERCOT, Texas, where battery energy storage capacity looks set to exceed the market for ancillary services sometime next year.

Additional reporting by Current.

Read Next

December 16, 2025
In this edition of the Energy-Storage.news US news roundup, EticaAG partners with Shell on battery immersion tech, Pacific Northwest National Laboratory begins utility-scale battery testing, and ON.Energy announces a transformer supply agreement.
December 16, 2025
 Utility Georgia Power has reached an agreement with the Public Interest Advocacy (PIA) staff of the Georgia Public Service Commission (PSC), that, if approved, will help lower energy costs and meet electricity demand in the state.
December 15, 2025
A new battery energy storage system (BESS) cybersecurity whitepaper from consultancy firm The Brattle Group and cybersecurity solutions provider Dragos claims that a single 100MW/400MWh BESS outage could result in US$1.2 million in monthly losses.
Premium
December 11, 2025
Energy-Storage.news Premium speaks with John Farrell, Co-Director of The Institute for Local Self-Reliance (ILSR), on rising utility costs and the role energy storage can play.
Premium
December 10, 2025
Last month was the first time since June that both pre-application submissions and full planning consent submissions for grid-scale UK BESS surpassed 1GWh – just before NESO announced the results of its grid connection queue reshuffle.