UK: High BM skip rate for BESS bemoaned as H1 revenues crash

LinkedIn
Twitter
Reddit
Facebook
Email

Concern has been raised by the industry about battery storage consistently being overlooked in the UK Balancing Mechanism (BM), as the sector’s average revenues plummeted in the first half of 2023.

On behalf of its 80 members, trade body Electricity Storage Network (ESN) penned an open letter to transmission system operator National Grid expressing concerns over the Balancing Mechanism’s (BM) average ‘skip rate’ of 80% for large-scale batteries between November 2022 and May 2023.

The BM is used to balance supply and demand on each half-hour trading period of the day, and an asset is ‘skipped’ if a more expensive bid or offer is taken up instead of that asset. Market intelligence firm Modo Energy said the skip rate for batteries was even higher in 2023 alone, at 91%.

The ESN’s letter, penned at the end of July, said these actions cost UK consumers around £150 million (US$190 million). It blamed outdated IT systems and manual processes in National Grid’s Control Room resulting in batteries consistently being skipped over in favour of larger, carbon-intensive and more expensive assets like fossil fuel gas plants.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The ESN called for ‘greater urgency and a step-up in engagement between ESO and the storage sector’ and ‘more accurate data on the dispatch of storage vs other technologies, including making the Dispatch Transparency dataset, which states ESO’s reasons for skips, more transparent’.

It comes as the UK battery storage sector saw average revenues per MW plummet in the first six months of 2023 compared with the same period last year. Energy-Storage.news has been told this anecdotally by industry sources while Modo has published numbers on it.

The firm’s Revenue Benchmark for July was £5,892/MW (US$7,500/MW), up 54% from the previous month but down around two-thirds from a year prior. Across the first half of the year, Modo’s monthly benchmark was down a similar amount.

Energy-Storage.news reported on Modo’s analysis of ancillary service Firm Frequency Response (FFR) auction prices hitting a 3-year low in May, in the “surest sign yet that saturation is starting to bite”, Modo commercial data analyst Shaniyaa Holness-Mckenzie said at the time.

The topic of market saturation has come up a lot when discussing ERCOT, Texas, where battery energy storage capacity looks set to exceed the market for ancillary services sometime next year.

Additional reporting by Current.

Read Next

October 23, 2026
Tech giant Google and distributed energy resource (DER) platform Voltus have announced an expanded agreement to build a 1GW virtual power plant (VPP) in the US.
October 23, 2026
German home energy storage and virtual power plant (VPP) company sonnen GmbH, sold by gas major Shell in August, has filed for insolvency.
October 22, 2026
In recent North American sodium-ion news, Hithium is entering the Canadian market with two BESS solutions, while Peak Energy has closed a Series B financing round led by GM.
Premium
October 22, 2026
BESS investments in the French market are moving to longer durations with saturation expected to hit the secondary reserve market, currently the main way operational projects make their money.
October 22, 2026
Science safety leader UL Solutions has announced a new certification pathway intended to help manufacturers of modular direct current (DC) battery energy storage systems (BESS).